ROADWAY ACTIVITY REPORT FOR LOWER EAST AND UPPER CUMBERLAND (OCT 23 – 29)
BLEDSOE COUNTY SR-30 and SR-443, the grading, drainage, stream relocation, widening, and resurfacing on Summer City Road: The contractor will be performing grade work and widening on Summer City Road in Bledsoe County. This work will narrow the lanes at LM 2.0 and LM 4.3 and will leave both lanes open to traffic. Please slow down and use caution when driving through the work zone. [Rogers Group, Inc./Dunlap/CNY153]
BRADLEY COUNTY I-75 [15.35-19.309] from MM 31 to MM 35 (McMinn County Line) resurfacing: The contractor will continue paving operations. This work will require temporary lane closures in both directions, which will occur Sunday nights through Friday nights, 8 PM to 6 AM. Motorists should exercise caution and pay attention to construction signage. The speed limit will be reduced during paving operations. [Wright Brothers Construction Company, Inc./Chattanooga West/CNY261]
BRADLEY COUNTY SR-40 [5.1-9.7] from Lyles Rd. to Bradley-Polk County Line resurfacing: During this reporting period, the contractor will continue resurfacing work on SR-40. Temporary lane closures will be necessary during daytime hours on weekdays while work is performed. Motorists should use caution when traveling through the work zone and be aware of equipment in the area. [APAC – Atlantic, Inc./Cleveland/CNZ020]
BRADLEY COUNTY SR-60 widening from the 4-lane north of I-75 (LM 17.2) to SR-306 (LM19.9): During this reporting period, the contractor will perform punch list work on SR-60 in Bradley County. Intermittent lane closures may be necessary while work occurs.
[Summers-Taylor, Inc./Cleveland/CNV130]
BRADLEY COUNTY SR-60 [13.1-13.28] at Benton Pike safety improvements: During this reporting period, improvements on the SR-60 North exit to Benton Pike will continue. Expect the roadway to be reduced to one lane weekdays between the hours of 8:00 AM – 3:30 PM. The SR-60 North exit ramp to Benton Pike will be closed for the duration of the project. A signed detour is in place.
[Wright Brothers Construction Company, Inc./Cleveland/CNZ183]
BRADLEY COUNTY SR-74 [11.445-11.83] from Whaley Road to SR-60 APD-40 drainage improvements: During this reporting period, the contractor will continue clearing and grubbing on SR-74 while installing EPSC measures. Intermittent flagging operations and shoulder closures will be necessary periodically. Motorists should use caution and reduce speed when traveling through the work zone. [APAC – Atlantic, Inc./Cleveland/CNZ243]
CAMPBELL, COFFEE, DAVIDSON, DICKSON, GILES, GREENE, HAYWOOD, KNOX, MCMINN, SHELBY, AND WILLIAMSON COUNTY. The installation of Weigh-in-Motion technology at 28 sites on various Interstate and State Routes.: No Region 2 Lane Closures this week on CNX913. [Davis H. Elliot Construction Company, Inc./Maint – R2/CNX913]
CANNON COUNTY SR-281 [0-4.51] from SR-53 to Todd Rd resurfacing: The contractor will have lane closures during daylight hours as needed from 5 AM to 9 PM for punch list and project wrap-up operations as needed. Flaggers will be present during the lane closure operations, and at least one lane will remain open at all times. [Rogers Group, Inc./McMinnville/CNZ066]
COFFEE COUNTY I-24 (MM 117) construction of an overpass carrying Wattendorf Memorial Highway/AEDC Road, including grading, drainage, retaining walls, and paving: Drivers can expect short-term flagging operations for trucks entering and exiting the work zone on Wattendorf Highway. Please use caution when traveling through the work zone.
[Jones Bros. Contractors, LLC/Tullahoma/CNZ029]
COFFEE COUNTY I-24 resurfacing from east of SR-2 (US-41) (LM 8.9) to near SR-55 (LM 14.8), including bridge expansion joint repairs and thin epoxy overlay: Nightly alternating lane closures will continue on I-24 from 7 PM-6 AM for resurfacing operations. One lane in each direction will be maintained at all times. [Rogers Group, Inc./Tullahoma/CNY262]
COFFEE COUNTY I-24 TDOT Maintenance eastbound at MM 113.8: Bridge repair operations will be completed on 10/28/2025 beginning at 9 AM and lasting until 10 AM. This work will involve removing a concrete form from a repaired overpass beam. Traffic control and law enforcement will be used in the area for a traffic advisory.
COFFEE COUNTY SR-55 construction from First Avenue (LM 2.0) to SR-16 (US-41A, N. Jackson St, LM 2.6) in Tullahoma: Phase 1 of roadway widening and bridge replacement on SR-55 (Wilson Ave.) will continue this week. Contractor may use temporary lane shifts to complete storm structure installations. Phase 1 traffic shift has reduced lanes from 3 to 2 from Cedar Lane to near Grau Lane in order to continue bridge replacement and storm drainage work.
[Dement Construction Company, LLC/Tullahoma/CNX912]
COFFEE COUNTY SR-55 repair of the bridge over the Little Duck River (LM 14.0): Lanes are reduced to one lane in each direction across the SR-55 bridge over the Little Duck River for bridge repair work. This lane reduction will be in place until work is complete in Fall 2025. [Mid-State Construction Company, Inc./Tullahoma/CNX412]
CUMBERLAND COUNTY I-40 [304-306] from Putnam County Line to near parking area resurfacing and bridge repair: The contractor will be performing shoulder work and pavement marking installations nightly on I-40 from MM 304 to MM 307 from 7 PM to 6 AM. During this work, one lane in each direction will be closed. Motorists should use caution as they approach the work zone and should prepare to encounter slow or stopped traffic. [Rogers Group, Inc./Cookeville/CNZ104]
CUMBERLAND COUNTY SR-1 (US-70) construction of bridge over the Obed River (LM 12.7): Construction activities may take place on SR-1 (US-70) over the Obed River bridge. Construction crews will be working outside of the roadway to complete remaining work activities. Traffic should be cautious of construction equipment near the shoulders. The contractor may need to flag traffic to move equipment or vehicles across the road. [Whaley Construction, LLC/Crossville/CNX110]
CUMBERLAND COUNTY SR-28 (US-127) bridge construction and paving from north of I-40 (LM 17.8) to near Potato Farm Road (LM 22.7): The contractor continues grading activities throughout the project limits. Temporary lane closures and/or periodic traffic stoppages will be necessary for construction activities. The contractor has scheduled paving operations beginning on the north end of the project on the proposed alignment. The contractor has closed North Grace Hill Drive at the existing intersection of SR-28 (US-127) for construction activities. Motorists should utilize South Grace Hill Drive as the detour with appropriate signs. Traffic has been moved to a temporary alignment on Plateau Road and a permanent alignment on Potato Farm Road. Flaggers and advanced warning signs will accompany any closures. Motorists should use caution when traveling through the work zone as traffic patterns change. [Jones Bros. Contractors, LLC/Crossville/CNV009]
CUMBERLAND COUNTY SR-298 [8.35-9.02] from north of Catoosa Canyon Dr to south of Obed Pines Rd construction of a small drainage structure: The contractor continues construction activities on Genesis Road (SR-298). Both lanes of Genesis Road (SR-298) at LM 8.35 to LM 9.02 have been closed and will be closed for the duration of the project with a posted detour route along SR-28 (US-127) and SR-62. The contractor will be working to replace a culvert underneath Genesis Road and installing retaining walls. RESTRICTIONS: Both lanes of Genesis Road (SR-298) are closed from LM 8.35 to LM 9.02. [J. Hill Excavating, LLC/Crossville/CNZ103]
CUMBERLAND COUNTY SR-462 from SR-28 (US-127N / LM 3.1) to SR-298 (Genesis Road / LM 4.6) in Crossville: Construction may take place as the contractor finishes the remaining small items. Activities may require temporary lane closures and/or traffic stoppages on Interstate Drive (SR-462), as well as short-term closures of city streets. Flagging operations will accompany these closures with appropriate signs. Motorists should use caution when traveling through the work zone.
[Rogers Group, Inc./Crossville/CNV010]
CUMBERLAND COUNTY SR-68 [0.34-5.58] from near SR-28 (US-127) to near Wiley Ford Road resurfacing: The contractor will be performing paving activities along SR-68 from near SR-28 (LM 0.34) to near Wiley Ford Road (LM 5.58). During these operations, a temporary lane closure will be utilized with flaggers and signs. Motorists should use caution when traveling through the project limits. [Rogers Group, Inc./Crossville/CNZ135]
CUMBERLAND AND FENTRESS COUNTY SR-28 (US-127) widening from near N. Lowe Rd (LM 29.2) to north of SR-62 (LM 1.9): The contractor has shifted traffic to phase 2 on the newly constructed portions of SR-28, LM 0.90 to 1.98 in Fentress County. Work will proceed on the existing alignment of SR-28. Flaggers are being used intermittently as needed to control traffic through the work zone. Motorists are encouraged to use caution, be aware of new traffic signs and pavement markings, and watch for construction equipment and personnel throughout the project.
[Jones Bros. Contractors, LLC/Cookeville/CNV300]
DEKALB COUNTY SR-26 (SPARTA HWY.) TDOT Contractor eastbound at LM 24.58: A TDOT contractor will be conducting an inspection of Sligo Bridge, SR-26 over Caney Fork River on 10/29/25. This will result in closure of the eastbound lane and shoulder from 9 AM until 3 PM. Automatic Flagging Devices will be present to direct traffic through the work zone. Motorists are advised to approach the bridge with caution and be prepared to stop as needed.
DEKALB COUNTY SR-26 (US-70) grading, drainage, and construction of retaining walls and paving from near SR-53 (LM 2) to near SR-96 (LM 6.1): The contractor continues grading and construction activities throughout the project. Temporary lane closures and periodic traffic stoppages will be necessary for construction activities, and motorists should be prepared to stop while traveling through the work zone. Motorists are encouraged to obey the posted speed limit and to watch for construction equipment and personnel adjacent to the roadway. The West end of Old Liberty Road will be closed to through traffic due to construction activities. Motorists and EMS will need to use the East entrance of Old Liberty Road to gain access and follow detour signs.
[Twin K Construction/Cookeville/CNV012]
DEKALB COUNTY SR-26 [10.88-13.25] from Near East Main Street to Trapp Lane resurfacing: The contractor will be milling and paving along SR-26. During this work, temporary lane closures will be used, and motorists are expected to follow all signage and expect delays. Motorists should use caution will traveling through the work zone. [Tinsley Asphalt, LLC /Cookeville/CNZ136]
HAMILTON COUNTY I-124 (US-27) from I-24 Interchange to South of the Tennessee River Bridge: Daily lane closures are possible between 9 AM and 3:30 PM as the contractor works along the ramps and 4th Street. Motorists are advised to reduce speed in the work zone and watch for flaggers assisting with traffic control. [Stansell Electric Company, Inc./Chattanooga East/CNY900]
HAMILTON COUNTY I-75 at I-24 Interchange Reconstruction Phase 2: Nightly Lane closures will occur on this project, 9 PM to 6 AM, on I-75 North and South between Exit 1 (East Ridge) and Exit 3A (East Brainerd Road/ SR-320) and on I-24 East and West from Germantown Road to Spring Creek Road, MM182 to MM185, for various construction activities. These closures may temporarily reduce traffic to a single lane. Uniformed police officers will be present in these work zones to assist with traffic management and to enforce traffic laws. (Note: Nighttime Lane closures (9 PM to 6 AM) of I-24 West and East should be expected between Germantown Road and Spring Creek Road on Thursday (10/23) and from Sunday (10/26) to Thursday (10/30) next week for paving as well as painting and texture coating of retaining and noise walls. At times, traffic may be temporarily reduced to a single lane while this work is taking place. As paving of traffic lanes progresses, it will be necessary to temporarily close entrance and exit ramps along I-24 for crews to safely perform their work. Message boards and detours will be posted to guide traffic to the next available ramp.) It may also be necessary to do short-duration (15 to 30 minutes) rolling roadblocks during the day or night for patching potholes, clearing debris or repairing guardrails, attenuators, etc. Portions of the left lane on North and South Terrace between Germantown Road and Spring Creek Road will remain closed for the installation of drainage structures, sanitary sewers, retaining and noise wall construction.
[Wright Brothers Construction Company, Inc./Maj Prj – Blevins/DB2101]
HAMILTON COUNTY I-75 at the Hamilton Place Mall interchange: The SR-153 southbound ramp to I-75 northbound has been reduced to one lane. Traffic shifts have been implemented on I-75 northbound, Shallowford Road entrance ramps, Shallowford Road exit ramps, and the Hamilton Place Mall exit ramp. Hamilton Loop Road is closed for retaining wall construction and storm drainage installation between the intersections near Markman’s Jewelers and Texas Roadhouse. The contractor has implemented a traffic shift on Hamilton Place Blvd., shifting NB and SB traffic to the east side of the existing roadway from near the I-75 SB on-ramp to near Bams Drive for the installation of storm drainage. The contractor will maintain 1 lane of traffic in each direction throughout this area. The speed limit has been reduced on I-75 throughout the project limits. Nightly lane closures are permitted 8 PM to 6 AM. Motorists should use caution, paying attention to construction signage and watching for construction vehicles and personnel.
[Summers-Taylor, Inc./Chattanooga West/CNX358]
HAMILTON COUNTY I-75 [4.2-4.5] from Exit 4A to SR-153 to Exit 3 to East Brainerd Road box culvert rehabilitation: The right shoulder of SB I-75 is closed with concrete barrier rail in place. Drivers should watch for construction vehicles entering and exiting the interstate. Two SB lanes will be closed on Thursday Night, 10/23/25, between the hours of 8 PM and 6 AM.
[Wright Brothers Construction Company, Inc./Chattanooga East/CNZ186]
HAMILTON COUNTY SR-2 (LEE HWY.) Utility Work both directions from LM 0.0 to LM .74: Flagging assisted lane closures on Lee Hwy (OE479) from near the entryway for McKay’s to the end of Lee Hwy at General Shale Brick & Building Materials. Motorists should reduce speed and be prepared to stop. Trucks, signage, flaggers, and barrels/cones will be present, 09/08/25 through 11/10/25 from 7 am – 5 pm/ [2024-297]
HAMILTON COUNTY SR-2 (LEE HWY.) Utility Work both directions from LM 18.80 to LM 18.86: Flagger-assisted lane closures on SR-2 (Lee Hwy) between McCutcheon Rd and Elm Dr. Motorists should reduce speed and be prepared to stop. Trucks, arrow boards/message boards, flaggers, and barrels/cones will be present, 10/2/25 through 11/10/25 from 9 am – 2 pm. [2024-338]
HAMILTON COUNTY SR-2 (W. 20TH ST.) Utility Work both directions from LM 7.52 to LM 7.85: Eastbound and Westbound Lane closures on SR-2 (W. 20th St) between Williams St. and Read Ave. Motorists should reduce speed and be prepared to stop. Arrow boards/message boards, flaggers, and barrels/cones will be present, 10/27/25, with a rain date of 10/28/25 from 9 am – 2 pm. [2025-731]
HAMILTON COUNTY SR-2 [2.73-3.19] from Wauhatchie United Methodist Church to Brown’s Ferry safety improvements: The contractor will be working between the hours of 8 PM and 6 AM to finish up roadway striping. [APAC – Atlantic, Inc./Chattanooga East/CNZ107]
HAMILTON COUNTY SR-29 [20.72-25.756] from SR-111 to Old Dayton Pk. Resurfacing: The contractor is resurfacing US-27 requiring temporary lane closures throughout the project length. The contractor’s schedule is 7 AM to 7 PM and weather dependent. Some work may be completed at night to facilitate the project schedule. [Rogers Group, Inc./Chattanooga West/CNZ034]
HAMILTON COUNTY SR-317 (Apison Pike) improvement project from SR-321 (Ooltewah-Ringgold Road) to east of Layton Lane: Lane closures and flagging operations will be required on SR-317 during daytime hours. [Wright Brothers Construction Company, Inc./Chattanooga East/CNT336]
HAMILTON COUNTY SR-8 [10.14-11.96] from Frazier Ave to Signal Mountain Blvd resurfacing: Contractor will be finishing roadway striping at night. Traffic may be detoured around intersections to complete work. [APAC – Atlantic, Inc./Chattanooga East/CNZ138]
HAMILTON COUNTY SR-8 [11.67-11.75] from Stringers Ridge Tunnel to Stringers Ridge Tunnel Cleaning: The Stringers Ridge Tunnel will be closed 10/22/2025 from 8 PM to 6 AM for cleaning. A detour will be in effect during the closures to direct traffic to alternative routes. This work is weather permitting. [Diamond Specialized, Inc./Chattanooga West/CNZ133]
HAMILTON COUNTY SR-8 [5.04-5.27] from Bachman Tubes to Bachman Tubes Tunnel Cleaning: The Bachman Tunnel will be closed 10/23/2025 from 8 PM to 6 AM for cleaning. A detour will in effect during the closures to direct traffic to alternative routes. This work is weather permitting. [Diamond Specialized, Inc./Chattanooga West/CNZ133]
HAMILTON COUNTY SR-8 [8.97-10.14] from MLK to Frazier Avenue resurfacing: Contractor will be finishing roadway striping. Traffic may be detoured around intersections to complete work.
[APAC – Atlantic, Inc./Chattanooga East/CNZ107]
JACKSON COUNTY SR-135 [15.74-20.76] from SR-56 to Clay County Line resurfacing: The contractor will continue paving operations along SR-135. During this work, temporary lane closures will be used with flaggers present. Signs warning of the closures will be in place. Motorists should use caution as they approach the work zone and should prepare to stop and follow the directions of the flagger. [Rogers Group, Inc./Cookeville/CNZ139]
MARION COUNTY I-24 [156.4-160.2] from 156.4 to 160.2 resurfacing: The contractor will be performing resurfacing operations on I-24 EB and WB in Marion County from MM 156.4 East of SR-28 to MM 160.2 West of the Tennessee River. This work will require single lane closures, leaving one lane open in each direction each night worked. Resurfacing operations will be Sunday through Thursday from 6 PM CT – 5 AM CT. Please use caution when driving through the work zones.
[Talley Construction Company, Inc./Dunlap/CNZ108]
MARION COUNTY SR-108 [2.8-3.24] slide mitigation: The contractor will be performing slide mitigation operations, including grading, drainage and paving on SR-108 in Marion County at LM 2.8. The roadway will be reduced to one lane controlled by temporary traffic signals. The project completion date is 08/31/2027. Please use caution when driving through the work zone.
[Wright Brothers Construction Company, Inc./Dunlap/CNZ226]
MARION COUNTY SR-156 repair of bridge over Tennessee River, LM 15.2: The contractor will be performing painting operations and structural repairs on the SR-156 bridge over the Tennessee River in South Pittsburg. This work will require intermittent lane closures controlled by flaggers or a temporary traffic signal, leaving one lane open. Please use caution when driving through the work zone. [Olympus Painting Contractors Inc./Dunlap/CNY063]
MARION COUNTY SR-2 [17.2-17.3] from 17.2 to 17.3 construction: The contractor will be performing grading and drainage operations on SR-2 in Marion County near LM 17.25. This work will require a lane shift for the EB traffic; the WB traffic will be unaffected. Please slow down and use caution when driving through the work zone. [Talley Construction Company, Inc./Dunlap/CNZ244]
MARION COUNTY SR-27 (US-72) resurfacing from the Alabama State Line (LM 0) to north of SR-156 (LM 2.7): The contractor will be performing paving operations on SR-27 EB and WB in Marion County from the Alabama state line to north of SR-156. This work will require single lane closures, leaving one lane open in each direction during daytime work hours. Please use caution when driving through the work zones. [Tinsley Asphalt, LLC /Dunlap/CNZ036]
MCMINN COUNTY I-75 [0-2.06] from MM 35 (Bradley County Line) to MM 37 resurfacing: The contractor will continue paving operations. This work will require temporary lane closures in both directions, which will occur Sunday nights through Friday nights, 8 PM to 6 AM. Motorists should exercise caution and pay attention to construction signage. The speed limit will be reduced during paving operations. [Wright Brothers Construction Company, Inc./Chattanooga West/CNY261]
MCMINN COUNTY I-75 [2.06-4.32] from MM 37 to MM 39.5 resurfacing: The contractor will continue paving operations. This work will require temporary lane closures in both directions, which will occur Sunday nights through Friday nights, 8 PM to 6 AM. Motorists should exercise caution and pay attention to construction signage. The speed limit will be reduced during paving operations.
[Wright Brothers Construction Company, Inc./Chattanooga West/CNZ109]
MCMINN COUNTY SR-39 construction of a bridge over Middle Creek (LM 13.4): During this reporting period, the contractor will be flagging the roadway to perform work. This flagging operation will only occur during daytime hours. [Whaley Construction, LLC/Chattanooga East/CNX069]
MCMINN COUNTY SR-39 from west of Cook Drive to SR-30 and from SR-310 to the Monroe County Line: During this reporting period, the contractor will complete punch list work on SR-39. Motorists should be aware of workers in the area performing this work. Intermittent lane closures and flagging operations around the work area will be necessary.
[Rogers Group, Inc./Cleveland/CNZ038]
MEIGS COUNTY SR-58 (STATE HWY. 58) Utility Work both directions from LM 0.01 to LM 0.30: Flagging assisted lane closures on SR 58 between Intersection HWY 60 and SR 58 to Gunstocker Rd. Motorists should reduce speed and be prepared to stop. Trucks, signage, flaggers, and barrels/cones will be present, 10/27/25 through 11/7/25 from 9 am – 2 pm [2025-707]
POLK COUNTY SR-68 construction of bridge over Brush Creek (LM 16.4): During this update period, the contractor will continue punch list work on SR-68 in Polk County. Intermittent lane closures may be necessary to complete this work.
[Wright Brothers Construction Company, Inc./Cleveland/CNX347]
POLK COUNTY SR-68 over SR-40 the construction of bridges: During this reporting period, the contractor will continue construction on the SR-68 North bridge. All SR-68 traffic is using the existing SR-68 South bridge while construction occurs on the new SR-68 North bridge. All SR-40/SR-68 interchange traffic will utilize the SR-68 South interchange ramps. A temporary 3-way stop has been implemented at the intersection of the SR-40 interchange ramp and SR-68. Motorists are encouraged to slow down when entering the construction zone and look out for new stop signs on SR-68 near the SR-40/SR-68 interchange. [Wright Brothers Construction Company, Inc./Cleveland/CNZ042]
PUTNAM COUNTY I-40 Utility Work, both directions from MM 287.0 to MM 297.0: Law Enforcement assisted rolling roadblock between Exit 287 eastbound and Exit 297 (near Rocky Point overpass) westbound. Message boards, signage, and law enforcement vehicles will be present. Motorists should be aware of personnel and equipment, reduce speed, and be prepared to stop. 10/26/25 between 6:00 am and 9:00 am. [2023-428]
PUTNAM COUNTY I-40 [300-304] from West of SR-24 to Cumberland County Line resurfacing and bridge repair: The contractor will be performing shoulder work and pavement marking installations nightly on I-40 from MM 300 to MM 304 from 7 PM to 6 AM. During this work, one lane in each direction will be closed. In addition, the on and off ramps may be closed intermittently to allow the contractor to work on the ramps. Signs and message boards warning of the closures will be in place. Motorists should use caution as they approach the work zone and should prepare to encounter slow or stopped traffic. [Rogers Group, Inc./Cookeville/CNZ104]
PUTNAM COUNTY SR-111 (STATE HWY. 111) TDOT Maintenance southbound at LM 3.53: Starting 10/23/25 at 7:00 AM, SR-111 southbound will be reduced to one lane as construction begins on a new turning lane. This will be reduced to one lane until the project is completed. Motorists are encouraged to follow signage and to use caution when in the area.
PUTNAM COUNTY SR-136 (S. JEFFERSON AVE.) Utility Work both directions from LM 2.55 to LM 2.75: Northbound and southbound lane closures on SR-136 (S Jefferson Ave) between Spring Street Town Square to I-40. Motorists should reduce speed and be prepared to stop. Arrow boards/message boards, flaggers, and barrels/cones will be present, 11/14/24 through 11/04/25 from 9 am – 2 pm. [2024-640]
PUTNAM COUNTY SR-136 construction from north of the SR-111 interchange to south of the I-40 interchange: The contractor continues grading activities throughout the project. Temporary lane closures and/or periodic traffic stoppages will be necessary for construction activities. Bunker Hill Rd is closed at the intersection of SR-136 with detour signs to utilize Henley Dr. Motorists are encouraged to use caution while traveling through the work zone and be aware of construction personnel and equipment adjacent to the roadway. [Rogers Group, Inc./Cookeville/CNV284]
PUTNAM COUNTY SR-84 (CALFKILLER HWY.) Utility Work both directions from LM 1.0 to LM 8.0: Flagger-assisted lane closures on SR-84 (Calfkiller Hwy) from the White County line to Hidden Acres Road. Motorists should reduce speed and be prepared to stop. Trucks, arrow board/message boards, flaggers, and barrels/cones will be present, 04/24/25 through 11/30/25 from 8 am – 3 pm. [2023-577]
REGION 2 Dynamic Message Sign (DMS) Life Cycle Replacement: Daily outside shoulder closures will take place on Bradley I-75 NB between MM 27 and MM 34 and McMinn I-75 SB at MM 45 and MM 35, and Marion County I-24 WB at MM 156. Trucks will be entering and exiting the work zone during daytime hours. On 10/26, the contractor will close the left lane in Marion County on I-24 WB at MM 156 between the hours of 8 PM and 6 AM. Starting 10/27 through 10/30, the contractor will be closing the left lane on Bradley County I-75 NB between MM 25 and MM 34 between the hours of 8 PM and 6 AM. [Davis H. Elliot Construction Company, Inc./Chattanooga East/CNX413]
REGION 2 preventative and unscheduled maintenance of Chattanooga SmartWay Intelligent Transportation System: The contractor may have short-term shoulder and/or lane closures to perform preventative or unscheduled maintenance to the local SmartWay Intelligent Transportation System. At least one travel lane will always remain open to traffic.
[Lumin8 Transportation Technologies, LLC/Chattanooga East/CNX270]
REGION 2 Snow-plowable marker re-lensing: The contractor will start snow-plowable lens replacement on 09/15/2025 on the following routes: Picket County SR-28 from LM 1.590 – 7.140, SR-52 from LM 0.000 – 2.260, SR-111 from LM 0.000 – 12.055, SR-154 from LM 0.000 – 5.726, SR-295 from LM 0.000 – 5.030, and SR-325 from LM 0.000 – 12.625, and Fentress County SR-28 from LM 0.000 – 33.580, SR-52 from LM 4.420 – 13.600, SR-52 from LM 17.620 – 27.930, SR-62 from LM 0.000 – 12.710, SR-85 from LM 0.000 – 11.010, SR-154 from LM 0.000 – 13.480, SR-296 from LM 0.000 – 3.030, SR-297 from LM 0.000 – 8.790, and SR-325 from LM 0.000 – 2.540. The contractor is expected to perform this work in the evening (8 PM – 6 AM) and will be utilizing a mobile operation. Motorists should use caution and expect delays when contract crews are present.
[W.L. Markers Inc./Cookeville/CNZ053]
REGION 2 The crack sealing at various locations on various State Routes: The contractor will have lane closures between 5 AM and 9 PM for crack sealing operations. Work will continue 7 days per week unless the contractor stops for weather or other logistical purposes. Locations: Bledsoe County SR-30 LM 0.0 to 10.40, Cumberland County SR-28 LM 14.96 to 8.25, Overton County SR-111 LM 3.29 to 10.69, Clay County SR-82 LM 20.58 to 26.60, Putnam County SR-111 LM 0.00 to 2.03, White County SR-111 LM 13.52 to 18.72, Cannon County SR-145 LM 0.0 to 9.67 and SR-281 LM 4.51 to 6.07, Warren County SR-287 LM 10.00 to 14.32 and SR-56 LM 15.43 to 24.88
[Reynolds Sealing and Striping, Inc./McMinnville/CNZ143]
REGION 2 The drain cleaning on various Interstate and State Routes: Drain cleaning operations are planned on I-24. Temporary lane closures will be utilized to complete this work. These operations will occur at night, Monday through Thursday, between 8 PM and 6 AM.
[Sweeping Corporation of America, Inc./Chattanooga West/CNY226]
REGION 2 The on-call guardrail repair and new guardrail installation on various Interstate and State Routes: The contractor will have short-term shoulder and/or lane closures in order to perform guardrail repair. These closures will take place on the interstate nightly Sunday through Thursday from 7 PM to 6 AM and daily Monday through Friday on state routes. At least one travel lane will remain open to traffic at all times on the interstate, and flaggers will be present on state routes during any work that is performed.
[Reynolds Fence and Guardrail, Inc./McMinnville/CNZ112]
REGION 2 The sweeping on various Interstate and State Routes: Sweeping operations are planned throughout Region 2 this reporting period. Sweeping operations are mobile operations along the inside and outside shoulders with impacts to adjacent traffic lanes. These operations will occur at night between 8 PM and 6 AM for interstates and high traffic state routes, while daytime sweeping can be anticipated between 9 AM to 3 PM for lower traffic state routes.
[Sweeping Corporation of America, Inc./Chattanooga West/CNY210]
REGION 2 Thermoplastic retracing on various interstate and state routes: The contractor will be on site in Rhea County on SR-30 at SR-303, Clay County SR-51 at SR-52, SR-58 LM 17.430 – 17.830, Hamilton County SR-17 at LM 8.73, Hamilton County SR-317 at LM 0.517, Hamilton County SR-317 at SR-153 Interchange, Hamilton County SR-317 at LM 0.971, Hamilton County SR-317 at LM 1.308, Hamilton County SR-317 at LM 1.573 – 1.794, Rhea County SR-30 from SR-29 to Cottonport Road. During this work, the contractor will utilize a mobile operation with mobile message boards and an attenuator truck. Motorists are encouraged to slow down as they approach the work and should be aware of the potential of stopped or slowing traffic.
[Reynolds Sealing and Striping, Inc./Cookeville/CNZ054]
REGION 2 Various Interstate and SRs – Cable Barrier Repair: The contractor will have short-term shoulder and/or lane closures in order to perform cable barrier rail repair. These closures will take place on the interstate nightly Sunday through Thursday from 7 PM to 6 AM and daily Monday through Friday. At least one travel lane will remain open to traffic at all times. Typically, only a shoulder closure will be used in the median, but lane closures will be employed as needed.
[LU, Inc./McMinnville/CNY183]
RESTRICTIONS
CAMPBELL, COFFEE, DAVIDSON, DICKSON, GILES, GREENE, HAYWOOD, KNOX, MCMINN, SHELBY, AND WILLIAMSON COUNTY – CNX913:
CUMBERLAND COUNTY – CNZ103: Both lanes of Genesis Road (SR-298) are closed from LM 8.35 to LM 9.02.