MULTIPLE ROAD AND BRIDGE PROJECTS CREATE DELAYS AND CLOSURES ACROSS CUMBERLAND COUNTY
Full Closure and Detour on Highway 70 North
-
Highway 70 North (LM 15.06 to LM 15.6, near Crossville city limits to Seventh-Day Adventist Church and School): Both lanes are closed for the duration of a bridge replacement project over the Obed River led by Mid-State Construction Company, Inc. Crews are starting with general clearing and utility work before replacing the bridge. Drivers must follow the posted detour along Northside Drive and Sparta Highway.
I-40 and Connecting Bridge Work
-
I-40 (MM 304.4 to MM 306.6): Rogers Group, Inc. continues bridge repair and resurfacing within the median, with traffic shifted along the corridor and construction vehicles entering and exiting the work zone.
-
Highway 70 North (LM 0 to LM 0.16, from Putnam County Line to C189): Connected to bridge repair work near I-40 MM 304.6 / Highway 70 North LM 0.24 under Rogers Group, Inc., Highway 70 North is reduced to one lane with temporary traffic signals.
-
I-40 (MM 328.2 to MM 328.4, near Crab Orchard): Capital City Construction Services, LLC has begun bridge repairs primarily beneath I-40 over Main Street, closing one lane of Main Street under temporary signal control.
Resurfacing, Grading, and Widening on Local Highways
-
Sparta Highway (Deep Water Road to near POW Camp Road): Rogers Group, Inc. continues resurfacing, with daily weekday temporary lane closures and flagging expected Monday through Friday. Drivers are advised to consider alternate routes when needed.
-
Highway 127 (north of I-40 at LM 17.8 to near Potato Farm Road at LM 22.7): Jones Bros. Contractors, LLC continues grading and paving operations, with temporary lane closures or periodic traffic stoppages possible under flagger and signage control.
-
Highway 127 (Bledsoe-Cumberland County Line to north of SR-419): Rogers Group, Inc. continues resurfacing with daily temporary lane closures and flagging.
-
Highway 127 (Potato Farm Road to N. Lowe Road): Charles Blalock and Sons, Inc. continues installing construction signs ahead of clearing and grading for a widening project, with potential temporary lane closures or flagging.