ROADWAY ACTIVITY REPORT FOR LOWE REAST AND UPPER CUMBERLAND (NOV. 13 – 19)

BRADLEY COUNTY I-75 [15.35-19.309] from MM 31 to MM 35 (McMinn County Line) resurfacing: The contractor will continue paving operations. This work will require temporary lane closures in both directions, which will occur Sunday nights through Friday nights 8 PM to 6 AM. Motorists should exercise caution and pay attention to construction signage. The speed limit will be reduced during paving operations. [Wright Brothers Construction Company, Inc./Chattanooga West/CNY261]

BRADLEY COUNTY SR-40 [5.1-9.7] from Lyles Rd. to Bradley-Polk County Line resurfacing: During this reporting period, the contractor will begin final pavement marking work on SR-40. Temporary lane closures will be necessary during daytime hours on weekdays while work is performed. Motorists should use caution when traveling through the work zone and be aware of equipment in the area. [APAC – Atlantic, Inc./Cleveland/CNZ020]

BRADLEY COUNTY SR-60 widening from the 4-lane north of I-75 (LM 17.2) to SR-306 (LM19.9): During this reporting period, the contractor will perform punch list work on SR-60 in Bradley County. Intermittent lane closures may be necessary while work occurs.
[Summers-Taylor, Inc./Cleveland/CNV130]

BRADLEY COUNTY SR-74 [11.445-11.83] from Whaley Road to SR-60 APD-40 drainage improvements: During this reporting period, the contractor will continue storm drain installation and grading work on SR-74. Intermittent flagging operations and shoulder closures will be necessary periodically. Motorists should use caution and reduce speed when traveling through the work zone.
[APAC – Atlantic, Inc./Cleveland/CNZ243]

CAMPBELL, COFFEE, DAVIDSON, DICKSON, GILES, GREENE, HAYWOOD, KNOX, MCMINN, SHELBY, AND WILLIAMSON COUNTY The installation of Weigh-in-Motion technology at 28 sites on various Interstate and State Routes: No Region 2 Lane Closures this week on CNX913. [Davis H. Elliot Construction Company, Inc./Maint – R2/CNX913]

CLAY COUNTY SR-53 (GAINESBORO HWY.) TDOT Bridge Inspection both directions from LM 0.16 to LM 2.5: On Wednesday Nov 19th the Cookeville bridge inspection office will be inspecting two bridges in Clay County on SR053 at the 0.16 and at the 2.50 log miles. The southbound lane of SR-53 will be closed at LM 2.50 from 8 am until noon. The northbound lane of SR-53 will be closed at LM 0.16 from noon until 3:30 pm. Flaggers will direct traffic through the work zones at both locations.

CUMBERLAND COUNTY SR-24 [15.056-15.56] from Crossville city limits to Seventh-Day Adventist Church and School bridge replacement: The Contractor is scheduled to close SR-24 at LM 15.06 to LM 15.6. This closure will remain in place for the duration of the project. The posted detour is along SR-462 and SR-1. The Contractor will be working on general clearing activities and utility work initially. Once initial work is completed, the contractor will proceed with the replacement of the bridge over the Obed River. Motorists should use caution and utilize the posted detour.
[Mid-State Construction Company, Inc./Crossville/CNZ206]

CUMBERLAND COUNTY SR-28 (US-127 S.) Utility Work both directions from LM 0.44 to LM 5.94: Northbound and Southbound Lane closures on SR-28 (HWY 127 S.) between Lowes Gap Rd. and Willard Brown Rd. Motorists should reduce speed and be prepared to stop. Arrow board/message boards, flaggers, and barrels/cones will be present, 10/30/25 through 02/25/2026 from 9 am – 2 pm. [2025-659]

CUMBERLAND COUNTY SR-28 (US-127) bridge construction and paving from north of I-40 (LM 17.8) to near Potato Farm Road (LM 22.7): The contractor continues grading activities throughout the project limits. Temporary lane closures and/or periodic traffic stoppages will be necessary for construction activities. The contractor has scheduled paving operations beginning on the north end of the project on the proposed alignment. The contractor has closed North Grace Hill Drive at the existing intersection of SR-28 (US-127) for construction activities. Motorists should utilize South Grace Hill Drive as the detour with appropriate signs. Traffic has been moved to temporary alignment on Plateau Road and permanent alignment on Potato Farm Road. Flaggers and advanced warning signs will accompany any closures. Motorists should use caution when traveling through the work zone as traffic patterns change. [Jones Bros. Contractors, LLC/Crossville/CNV009]

CUMBERLAND COUNTY SR-298 [8.35-9.02] from north of Catoosa Canyon Dr to south of Obed Pines Rd construction of a small drainage structure: The contractor continues construction activities on Genesis Road (SR-298). Both lanes of Genesis Road (SR-298) at LM 8.35 to LM 9.02 have been closed and will be closed for the duration of the project with a posted detour route along SR-28 (US-127) and SR-62. The contractor will be working to replace a culvert underneath Genesis Road and installing retaining walls. RESTRICTIONS: Both lanes of Genesis Road (SR-298) are closed from LM 8.35 to LM 9.02. [J. Hill Excavating, LLC/Crossville/CNZ103]

CUMBERLAND COUNTY SR-462 from SR-28 (US-127N / LM 3.1) to SR-298 (Genesis Road / LM 4.6) in Crossville: The Contractor anticipates paving SR-28 northbound at the intersection of SR-462 at LM 16.7. Activities will require temporary lane closures and/or traffic stoppages on SR-28 and Interstate Drive (SR-462). Flagging operations will accompany these closures with appropriate signs. Motorists should use caution when traveling through the work zone.
[Rogers Group, Inc./Crossville/CNV010]

DEKALB COUNTY SR-26 (US-70) grading, drainage, and construction of retaining walls and paving from near SR-53 (LM 2) to near SR-96 (LM 6.1): The contractor continues grading and construction activities throughout the project. Temporary lane closures and periodic traffic stoppages will be necessary for construction activities and motorists should be prepared to stop while traveling through the work zone. Motorists are encouraged to obey posted speed limit and to watch for construction equipment and personnel adjacent to the roadway. The West end of Old Liberty Road will be closed to through traffic due to construction activities. Motorists and EMS will need to use the East entrance of Old Liberty Road to gain access and follow detour signs.
[Twin K Construction/Cookeville/CNV012]

DEKALB COUNTY SR-26 [10.88-13.25] from Near East Main Street to Trapp Lane resurfacing: The contractor will be onsite intermittently to complete remaining contract work and complete any punch list work. Daily lane closures may be utilized to facilitate this work, and motorists should follow all signage and expect delays. [Tinsley Asphalt, LLC /Cookeville/CNZ136]

GRUNDY COUNTY SR-50 (–) Utility Work both directions from LM 0.08 to LM 0.16: Flagging assisted lane closures on Hwy 50 (SR 50) between Coffee County Rd. and I-24 Exit 127. Motorists should reduce speed and be prepared to stop. Trucks, signage, flaggers, and barrels/cones will be present, 11/11/25 with a rain date of 11/19/25 from 9 am – 2 pm/ [2025-647]

HAMILTON COUNTY I-75 at I-24 Interchange Reconstruction Phase 2: Nightly Lane closures will regularly occur on this project, 9 PM to 6 AM, on I-75 North and South between Exit 1 (East Ridge) and Exit 3A (East Brainerd Road/ SR-320) and on I-24 East and West from Germantown Road to Spring Creek Road, MM182 to MM185, for various construction activities. These closures may temporarily reduce traffic to a single lane. Uniformed police officers will be present in these work zones to assist with traffic management and to enforce traffic laws. (Note: nighttime lane closures from 8 PM to 6 AM are scheduled on I-24 East and West between Germantown Road and the I-75 interchange for placement of asphalt paving from Thursday (11/13) through Thursday (11/20) of next week. Depending on weather and temperature conditions, the contractor will be paving every night on I-24, including this coming weekend to expedite final paving prior to the Thanksgiving holidays. At times, traffic may be temporarily reduced to a single lane while this work is taking place. As crews pave traffic lanes, it will be necessary to temporarily close entrance and exit ramps along I 24 for crews to safely perform their work. Message boards and detours will be posted to guide traffic to the next available ramp. Most of the remaining work items on this project are temperature and weather sensitive. If any of them are canceled due to inclement conditions, they will be rescheduled to take place on the next available day when adequate conditions exist.) It may also be necessary to do short duration (15 to 30 minutes) rolling roadblocks during the day or night for patching potholes, clearing debris or repairing guardrail, attenuators, etc. Portions of the left lane on North and South Terrace between Germantown Road and Spring Creek Road will remain closed for the installation of drainage structures, sanitary sewers, retaining and noise wall construction.
[Wright Brothers Construction Company, Inc./Maj Prj – Blevins/DB2101]

HAMILTON COUNTY I-75 at the Hamilton Place Mall interchange: The SR-153 southbound ramp to I-75 northbound has been reduced to one lane. Traffic shifts have been implemented on I-75 northbound, Shallowford Road entrance ramps, and Shallowford Road exit ramps and Hamilton Place Mall exit ramp. Hamilton Loop Road is closed for retaining wall construction and storm drainage installation between the intersections near Markman’s Jewelers and Texas Roadhouse. The contractor has implemented a traffic shift on Hamilton Place Blvd. shifting NB and SB traffic to the east side of the existing roadway from near the I-75 SB on-ramp to near Bams Drive for the installation of storm drainage. The contractor will maintain 1 lane of traffic in each direction throughout this area. On the nights of 11/13/25 through 11/14/25 the contractor will close the I-75 SB Entrance Ramp from Shallowford Road from 10 PM until 6 AM for bridge beam erection. The speed limit has been reduced on I-75 throughout the project limits. Nightly lane closures are permitted 8 PM to 6 AM. Motorists should use caution, paying attention to construction signage and watching for construction vehicles and personnel.
[Summers-Taylor, Inc./Chattanooga West/CNX358]

HAMILTON COUNTY SR-2 (BRAINERD RD.) Utility Work both directions from LM 12.93 to LM 13.03: Flagging assisted lane closures on Brainerd Rd. Between Germantown Rd. and Belvoir Rd. Motorists should reduce speed and be prepared to stop. Trucks, signage, flaggers, and barrels/cones will be present, 11/06/25 through 12/12/25 from 9 am – 2 pm/ [2025-687]

HAMILTON COUNTY SR-2 (LEE HWY.) Utility Work both directions from LM 0.0 to LM 0.74: Flagging assisted lane closures on Lee Hwy (OE479) from near the entryway for McKay’s to the end of Lee Hwy at General shale Brick & Building Materials. Motorists should reduce speed and be prepared to stop. Trucks, signage, flaggers, and barrels/cones will be present, 09/08/25 through 11/19/25 from 7 am – 5 pm/ [2024-297]

HAMILTON COUNTY SR-2 (LEE HWY.) Utility Work both directions from LM 18.80 to LM 18.86: Flagger assisted lane closures on SR-2 (Lee Hwy) between McCutcheon Rd and Elm Dr. Motorists should reduce speed and be prepared to stop. Trucks, arrow board/message boards, flaggers, and barrels/cones will be present, 10/2/25 thru 11/19/25 from 9 am – 2 pm. [2024-338]

HAMILTON COUNTY SR-2 [11.86-11.63] from McCallie Tunnel to McCallie Tunnel Maintenance: The McCallie Tunnels will be cleaned 11/19/2025 from 8 PM to 6 AM, weather permitting. The contractor will clean one side at a time and flag traffic during the work. Motorists should expect delays. [Diamond Specialized, Inc./Chattanooga West/CNZ133]

HAMILTON COUNTY SR-29 [20.72-25.756] from SR-111 to Old Dayton Pk. Resurfacing: The contractor is resurfacing US-27 requiring temporary lane closures throughout the project length. The contractor’s schedule is 7 AM to 7 PM and weather dependent. Some work maybe completed at night to facilitate the project schedule. [Rogers Group, Inc./Chattanooga West/CNZ034]

HAMILTON COUNTY SR-320 (E. BRAINERD RD.) Utility Work both directions from LM 3.68 to LM 3.93: Flagger assisted lane closures on SR-320 (E. Brainerd) between Stanley Ave. and Kinsey Dr. Motorists should reduce speed and be prepared to stop. Trucks, arrow board/message boards, flaggers, and barrels/cones will be present on 11/17/25 through 11/18/25 from 9 am – 2 pm. [2025-819]

HAMILTON COUNTY SR-8 [11.67-11.75] from Stringers Ridge Tunnel to Stringers Ridge Tunnel  Cleaning: The Stringers Ridge Tunnel will be closed 11/19/2025 from 8 PM to 6 AM for cleaning. A detour will in effect during the closures to direct traffic to alternative routes. This work is weather permitting. [Diamond Specialized, Inc./Chattanooga West/CNZ133]

HAMILTON COUNTY SR-8 [5.04-5.27] from Bachman Tubes to Bachman Tubes Tunnel Cleaning: The Bachman Tunnel will be closed 11/20/2025 from 8 PM to 6 AM for cleaning. A detour will in effect during the closures to direct traffic to alternative routes. This work is weather permitting. [Diamond Specialized, Inc./Chattanooga West/CNZ133]

MARION COUNTY SR-108 [2.8-3.24] slide mitigation: The contractor will be performing slide mitigation operations, including grading, drainage and paving on SR-108 in Marion County at LM 2.8. The roadway will be reduced to one lane controlled by temporary traffic signals. The project completion date is 08/31/2027. Please use caution when driving through the work zone.
[Wright Brothers Construction Company, Inc./Dunlap/CNZ226]

MARION COUNTY SR-2 [17.2-17.3] from 17.2 to 17.3 construction: The contractor will be performing grading and drainage operations on SR-2 in Marion County near LM 17.25. This work will require a lane shift for the EB traffic, the WB traffic will be unaffected. Please slow down and use caution when driving through the work zone. [Talley Construction Company, Inc./Dunlap/CNZ244]

MCMINN COUNTY I-75 [0-2.06] from MM 35 (Bradley County Line) to MM 37 resurfacing: The contractor will continue paving operations. This work will require temporary lane closures in both directions, which will occur Sunday nights through Friday nights 8 PM to 6 AM. Motorists should exercise caution and pay attention to construction signage. The speed limit will be reduced during paving operations. [Wright Brothers Construction Company, Inc./Chattanooga West/CNY261]

MCMINN COUNTY I-75 [2.06-4.32] from MM 37 to MM 39.5 resurfacing: The contractor will continue paving operations. This work will require temporary lane closures in both directions, which will occur Sunday nights through Friday nights 8 PM to 6 AM. Motorists should exercise caution and pay attention to construction signage. The speed limit will be reduced during paving operations.
[Wright Brothers Construction Company, Inc./Chattanooga West/CNZ109]

MCMINN COUNTY SR-30 (DECATUR PK.) Utility Work both directions from LM 9.29 to LM 9.64: Flagging assisted lane closures on Decatur Pike between Oak St. and Howard St. Motorists should reduce speed and be prepared to stop. Trucks, signage, flaggers, and barrels/cones will be present, 11/17/2025 from 9AM to 2PM with a rain date of 11/21/2025from 9AM to 2PM [2025-712]

MCMINN COUNTY SR-30 (LILLARD HWY.) Utility Work both directions from LM 16.43 to LM 16.45: Northbound and southbound lane closures on SR-30 (David W. Lillard Hwy) at the intersection of Blair Branch Rd. and SR 30 (Daivid W. Lillar Hwy.) Motorists should reduce speed and be prepared to stop. Detour signage, arrow board/message boards, flaggers, and barrels/cones will be present, 11/17/25 through 12/19/25 from 9 am – 2 pm. [2025-483 and 2025-484]

MCMINN COUNTY SR-39 from west of Cook Drive to SR-30 and from SR-310 to the Monroe County Line: During this reporting period, the contractor will complete punch list work on SR-39. Motorists should be aware of workers in the area performing this work. Intermittent lane closures and flagging operations around the work area will be necessary.
[Rogers Group, Inc./Cleveland/CNZ038]

POLK COUNTY SR-68 construction of bridge over Brush Creek (LM 16.4): During this update period, the contractor will continue punch list work on SR-68 in Polk County. Intermittent lane closures may be necessary to complete this work.
[Wright Brothers Construction Company, Inc./Cleveland/CNX347]

POLK COUNTY SR-68 over SR-40 the construction of bridges: During this reporting period the contractor will continue construction on the SR-68 North bridge. All SR-68 traffic is using the existing SR-68 South bridge while construction occurs on the new SR-68 North bridge. All SR-40/SR-68 interchange traffic will utilize the SR-68 South interchange ramps. A temporary 3-way stop has been implemented at the intersection of the SR-40 interchange ramp and SR-68. Motorists are encouraged to slow down when entering the construction zone and look out for new stop signs on SR-68 near the SR-40/SR-68 interchange.
[Wright Brothers Construction Company, Inc./Cleveland/CNZ042]

PUTNAM COUNTY SR-111 (STATE HWY. 111) TDOT Maintenance southbound at LM 3.53: SR 111 southbound will continue to be reduced to one lane for the construction of a new turning lane. Expect the roadway to be reduced to one lane weekdays between the hours of 8 AM – 3 PM until the project is completed. Motorists are encouraged to follow signage and use caution when in the area.

PUTNAM COUNTY SR-136 construction from north of the SR-111 interchange to south of the I-40 interchange: The contractor continues grading activities throughout the project. Temporary lane closures and/or periodic traffic stoppages will be necessary for construction activities. Bunker Hill Rd is closed at the intersection of SR-136 with detour signs to utilize Henley Dr. Motorists are encouraged to use caution while traveling through the work zone and be aware of construction personnel and equipment adjacent to the roadway. [Rogers Group, Inc./Cookeville/CNV284]

PUTNAM COUNTY SR-24 (CROSSVILLE HWY.) Utility Work both directions from LM 35.55 to LM 38.09: Eastbound and Westbound Lane closures on SR-24 (Crossville Hwy.) between E. Wilder Ave. and Walker Farm Rd. Motorists should reduce speed and be prepared to stop. Arrow board/message boards, flaggers, and barrels/cones will be present, 11/06/25 through 05/06/2026 from 9 am – 2 pm. [2025-521]

PUTNAM COUNTY SR-84 (CALFKILLER HWY.) Utility Work both directions from LM 1.0 to LM 8.0: Flagger assisted lane closures on SR-84 (Calfkiller Hwy) from the White County line to Hidden Acres Road. Motorists should reduce speed and be prepared to stop. Trucks, arrow board/message boards, flaggers, and barrels/cones will be present, 04/24/25 through 11/30/25 from 8 am – 3 pm. [2023-577]

REGION 2 Dynamic Message Sign (DMS) Life Cycle Replacement: No lane closures this week.
[Davis H. Elliot Construction Company, Inc./Chattanooga East/CNX413]

REGION 2 Retracing of painted pavement markings: The contractor is expected to start paint retracing in the following counties: Bradley SR-60 from LM 3.850 – 8.200, Franklin SR-15 from LM 22.210 – 27.200, Marion SR-283 from LM 0.000 – 2.600. During this work the contractor will be utilizing a mobile operation with attenuators. Motorists should be aware of wet paint when crews are present and expect delays. [Reynolds Sealing and Striping, Inc./Cookeville/CNZ052]

REGION 2 Snow-plowable marker re-lensing: The contractor will start snow-plowable lens replacement on 09/15/2025 on the following routes: Picket County SR-28 from LM 1.590 – 7.140, SR-52 from LM 0.000 – 2.260, SR-111 from LM 0.000 – 12.055, SR-154 from LM 0.000 – 5.726, SR-295 from LM 0.000 – 5.030, and SR-325 from LM 0.000 – 12.625, and Fentress County SR-28 from LM 0.000 – 33.580, SR-52 from LM 4.420 – 13.600, SR-52 from LM 17.620 – 27.930, SR-62 from LM 0.000 – 12.710, SR-85 from LM 0.000 – 11.010, SR-154 from LM 0.000 – 13.480, SR-296 from LM 0.000 – 3.030, SR-297 from LM 0.000 – 8.790, and SR-325 from LM 0.000 – 2.540. The contractor is expected to perform this work in the evening (8 PM – 6 AM) and will be utilizing a mobile operation. Motorists should use caution and expect delays when contract crews are present.
[W.L. Markers Inc./Cookeville/CNZ053]

REGION 2 The crack sealing at various locations on various State Routes: The contractor will have lane closures between 5 AM and 9 PM for crack sealing operations. Work will continue 7 days per week unless the contractor stops for weather or other logistical purposes. Locations: Cumberland County SR-28 LM 14.96 to 8.25, Overton County SR-111 LM 3.29 to 10.69, Clay County SR-82 LM 20.58 to 26.60, Putnam County SR-111 LM 0.00 to 2.03
[Reynolds Sealing and Striping, Inc./McMinnville/CNZ143]

REGION 2 The on-call cable barrier repair on various Interstate and State Routes.: The contractor will have short term shoulder and/or lane closures in order to perform force account cable barrier rail repair. These closures will take place on the interstate nightly Sunday through Thursday from 7 PM to 6 AM as needed and daily Monday through Friday. At least one travel lane will remain open to traffic at all times. Typically, only shoulder closures will be used in the median, but lane closures will be employed as needed. [LU, Inc./McMinnville/CNZ205]

REGION 2 The on-call guardrail repair and new guardrail installation on various Interstate and State Routes: The contractor will have short-term shoulder and/or lane closures in order to perform guardrail repair. These closures will take place on the interstate nightly Sunday through Thursday from 7 PM to 6 AM and daily Monday through Friday on state routes. At least one travel lane will remain open to traffic at all times on the interstate, and flaggers will be present on state routes during any work that is performed.
[Reynolds Fence and Guardrail, Inc./McMinnville/CNZ112]

REGION 2 The sweeping on various Interstate and State Routes: Sweeping operations are planned throughout Region 2 this reporting period. Sweeping operations are mobile operations along the inside and outside shoulders with impacts to adjacent traffic lanes. These operations will occur at night between 8 PM and 6 AM for interstates and high traffic state routes, while daytime sweeping can be anticipated between 9 AM to 3 PM for lower traffic state routes.
[Sweeping Corporation of America, Inc./Chattanooga West/CNY210]

REGION 2 Thermoplastic retracing on various interstate and state routes: The contractor will be on site in Rhea County on SR-30 at SR-303, Clay County SR-51 at SR-52, SR-58 LM 17.430 – 17.830, Hamilton County SR-17 at LM 8.73, Hamilton County SR-317 at LM 0.517, Hamilton County SR-317 at SR-153 Interchange, Hamilton County SR-317 at LM 0.971, Hamilton County SR-317 at LM 1.308, Hamilton County SR-317 at LM 1.573 – 1.794, Rhea County SR-30 from SR-29 to Cottonport Road. During this work, the contractor will utilize a mobile operation with mobile message boards and an attenuator truck. Motorists are encouraged to slow down as they approach the work and should be aware of the potential of stopped or slowing traffic.
[Reynolds Sealing and Striping, Inc./Cookeville/CNZ054]

REGION 2 Various Interstate and SRs – Cable Barrier Repair: The contractor will have short-term shoulder and/or lane closures in order to perform cable barrier rail repair. These closures will take place on the interstate nightly Sunday through Thursday from 7 PM to 6 AM as needed and daily Monday through Friday. At least one travel lane will remain open to traffic at all times. Typically, only shoulder closures will be used in the median, but lane closures will be employed as needed.
[LU, Inc./McMinnville/CNY183]

WHITE COUNTY SR-111 (SPENCER HWY.) TDOT Maintenance southbound at LM 7.3: SR111 will be reduced to one lane for the widening and resurfacing of a turning lane. Expect the roadway to be reduced to one lane weekdays between the hours of 8 AM – 3 PM until the project is completed. Motorists are encouraged to follow signage and use caution when in the area.

RESTRICTIONS

CAMPBELL, COFFEE, DAVIDSON, DICKSON, GILES, GREENE, HAYWOOD, KNOX, MCMINN, SHELBY, AND WILLIAMSON COUNTY – CNX913:

CUMBERLAND COUNTY – CNZ103: Both lanes of Genesis Road (SR-298) are closed from LM 8.35 to LM 9.02.