ROADWAY ACTIVITY REPORT FOR LOWER EAST AND UPPER CUMBERLAND (FEB. 12 – 18)

BRADLEY COUNTY I-75 [15.35-19.309] from MM 31 to MM 35 (McMinn County Line) resurfacing: The contractor will continue paving operations. This work will require temporary lane closures in both directions, which will occur Sunday nights through Friday nights 8 PM to 6 AM. Motorists should exercise caution and pay attention to construction signage. The speed limit will be reduced during paving operations.
[Wright Brothers Construction Company, Inc./Chattanooga West/CNY261]

BRADLEY COUNTY SR-60 widening from the 4-lane north of I-75 (LM 17.2) to SR-306 (LM19.9): During this reporting period, the contractor will perform punch list work on SR-60 in Bradley County. Intermittent lane closures may be necessary while work occurs.
[Summers-Taylor, Inc./Cleveland/CNV130]

BRADLEY COUNTY SR-74 (SPRING PLACE RD.) Utility Work in both directions from LM 11.07 to LM 11.14: Flagging-assisted lane closures on SR-74 (Spring Place Rd) between Clayton LN and Durkee RD SE, Motorists should reduce speed and be prepared to stop. Trucks, signage, flaggers, and barrels/cones will be present, 12/18/25 through 06/18/2026 from 9 am – 2 pm [2025-736]

BRADLEY COUNTY SR-74 [11.445-11.83] from Whaley Road to SR-60 APD-40 drainage improvements: During this reporting period, the contractor will continue storm drain installation and grading work on SR-74. Intermittent flagging operations and shoulder closures will be necessary periodically. Motorists should use caution and reduce speed when traveling through the work zone.
[APAC – Atlantic, Inc./Cleveland/CNZ243]

CAMPBELL, COFFEE, DAVIDSON, DICKSON, GILES, GREENE, HAYWOOD, KNOX, MCMINN, SHELBY, AND WILLIAMSON COUNTY The installation of Weigh-in-Motion technology at 28 sites on various Interstate and State Routes: No Region 2 Lane Closures this week on CNX913. [Davis H. Elliot Construction Company, Inc./Maint – R2/CNX913]

COFFEE COUNTY I-24 (MM 117) construction of an overpass carrying Wattendorf Memorial Highway/AEDC Road, including grading, drainage, retaining walls, and paving: Drivers can expect short-term flagging operations for trucks entering and exiting the work zone on Wattendorf Highway. Please use caution when traveling through the work zone.
[Jones Bros. Contractors, LLC/Tullahoma/CNZ029]

COFFEE COUNTY I-24 TDOT Contractor both directions from MM 111 to MM 111.3: During this reporting period, the contractor from MM111-MM 11.34 will have the right shoulder closed as they work to locate some utilities.

COFFEE COUNTY SR-2 (HILLSBORO RD.) Utility Work both directions at LM 16.95: Northbound and Southbound Lane closures on SR-22 (Hillsboro Blvd) between Doak Rd and Asbury RD. Motorists should reduce speed and be prepared to stop. Arrow board/message boards, flaggers, and barrels/cones will be present, 02/11/2026 with a rain date of 02/12/2026 from 9 am – 2 pm. [2025-785]

COFFEE COUNTY SR-55 (MCMINNVILLE HWY.) TDOT Contractor both directions from LM 14.6 to LM 15.00: During this reporting period, from 8:30 AM-2:30 PM, the inside lane will be closed on SR55 in both directions from LM14.6 to LM15.0 so that the contractor can locate and find the depth of the existing waterline in the grass median on SR55.

COFFEE COUNTY SR-55 construction from First Avenue (LM 2.0) to SR-16 (US-41A, N. Jackson St, LM 2.6) in Tullahoma: Phase 2 of roadway widening and bridge replacement on SR-55 (Wilson Ave.) will continue this week. Traffic will be shifted on 02/12/26 from Big Springs Avenue to US-41A (North Jackson Street). Lanes will be reduced from 3 lanes to 2 with one lane in each direction throughout the project length after this shift. [Dement Construction Company, LLC/Tullahoma/CNX912]

CUMBERLAND COUNTY I-40 [304.4-306.6] from MM 304.4 to MM 306.6 bridge repair and resurfacing: The Contractor has started working on the bridge repair on I-40 at MM 304.6. Motorists should use caution in the area. [Rogers Group, Inc./Crossville/CNZ290]

CUMBERLAND COUNTY SR-1 (US-70 E.) TDOT Bridge Inspection eastbound at LM 34.19: A routine inspection of the SR-1 bridge over Piney Creek will require closure of the eastbound lane on Tuesday, February 17th and Wednesday, February 18, from 8 AM until 4 PM. Flaggers will direct traffic through the work zone. Motorists should be aware of temporary traffic control measures and be prepared to stop when approaching the bridge from either direction.

CUMBERLAND COUNTY SR-24 (US-70 N.) Utility Work both directions at LM 7.90: Northbound and Southbound Lane closures on SR-24 (HWY 70 N.) between Miller Ct and Newberry Rd. Motorists should reduce speed and be prepared to stop. Arrow board/message boards, flaggers, and barrels/cones will be present, 02/11/2026 with a rain date of 02/12/2026 from 9 am – 2 pm. [2025-1008]

CUMBERLAND COUNTY SR-24 [0-0.16] from Putnam County Line to C189 bridge repair: The Contractor has started working on the bridge repair on I-40 at MM 304.6 or SR-24 at LM 0.24. The Contractor is working behind guardrail. Once additional work begins, additional lane closures may be necessary. Motorists should use caution in the area.
[Rogers Group, Inc./Crossville/CNZ290]

CUMBERLAND COUNTY SR-24 [15.056-15.56] from Crossville city limits to Seventh-Day Adventist Church and School bridge replacement: The contractor has closed SR-24 at LM 15.06 to LM 15.6. This closure will remain in place for the duration of the project. The posted detour is along SR-462 and SR-1. The Contractor will be working on general clearing activities and utility work initially. Once initial work is completed, the Contractor will proceed with the replacement of the bridge over the Obed River. Motorists should use caution and utilize the posted detour. RESTRICTIONS: Both lanes of SR-24 are closed at LM 15.06 to LM 15.6.
[Mid-State Construction Company, Inc./Crossville/CNZ206]

CUMBERLAND COUNTY SR-28 (US-127 S.) Utility Work both directions from LM .44 to LM 5.94: Northbound and Southbound Lane closures on SR-28 (HWY 127 S.) between Lowes Gap Rd. and Willard Brown Rd. Motorists should reduce speed and be prepared to stop. Arrow board/message boards, flaggers, and barrels/cones will be present, 10/30/25 through 02/25/2026 from 9 am – 2 pm. [2025-659]

CUMBERLAND COUNTY SR-28 (US-127 S.) Utility Work both directions from LM .44 to LM 5.94: Northbound and Southbound Lane closures on SR-28 (HWY 127 S.) between Lowes Gap Rd. and Willard Brown Rd. Motorists should reduce speed and be prepared to stop. Arrow board/message boards, flaggers, and barrels/cones will be present, 10/30/25 through 02/25/2026 from 9 am – 2 pm. [2025-659]

CUMBERLAND COUNTY SR-28 (US-127) bridge construction and paving from north of I-40 (LM 17.8) to near Potato Farm Road (LM 22.7): The contractor continues grading activities throughout the project limits. Temporary lane closures and/or periodic traffic stoppages will be necessary for construction activities. The contractor has closed Lawson Road at the intersection of Cline Road to install a drainage pipe. A detour has been posted to utilize Tabor Loop. Flaggers and advanced warning signs will accompany any closures. Motorists should use caution when traveling through the work zone as traffic patterns change. [Jones Bros. Contractors, LLC/Crossville/CNV009]

CUMBERLAND COUNTY SR-299 (ROCKWOOD AIRPORT RD.) Utility Work both directions from LM 1.41 to LM 1.57: Northbound and Southbound Lane closures on SR-299 (Airport Road) at Golliher rd. near the airport Motorists should reduce speed and be prepared to stop. Arrow board/message boards, flaggers, and barrels/cones will be present, 02/16/2026 through 02/18/2026 with a rain date of 02/19/2026 from 9 am – 2 pm. [2025-925]

CUMBERLAND AND FENTRESS COUNTY SR-28 (US-127) widening from near N. Lowe Rd (LM 29.2) to north of SR-62 (LM 1.9): The contractor has shifted traffic to phase 2 on the newly constructed portions of SR-28 LM 0.90 to 1.98 in Fentress County. Work will proceed on the existing alignment of SR-28. Flaggers are being used intermittently as needed to control traffic through the work zone. Motorists are encouraged to use caution, be aware of new traffic signs and pavement markings, and watch for construction equipment and personnel throughout the project.
[Jones Bros. Contractors, LLC/Cookeville/CNV300]

DEKALB COUNTY SR-26 (US-70) grading, drainage, and construction of retaining walls and paving from near SR-53 (LM 2) to near SR-96 (LM 6.1): The contractor will continue normal working activities throughout the project limits. During this work, temporary lane closures are possible, and flaggers will be present. Motorists are encouraged to use caution while traveling through the work zone and should be aware of construction equipment adjacent to the roadway.
[Twin K Construction/Cookeville/CNV012]

FRANKLIN COUNTY SR-15 (S. COLLEGE ST.) Utility Work both directions at LM 16.05: Flagging- assisted lane closures on SR-15 (South College St.) between Highland Rd and Country Club Rd. Motorists should reduce speed and be prepared to stop. Trucks, signage, flaggers, and barrels/cones will be present, 02/02/2026 through 02/06/2026 from 9 am – 2 pm [2025-558)

HAMILTON COUNTY I-124 (US-27) from I-24 Interchange to South of the Tennessee River Bridge: Daily lane closures are possible between 9 AM and 3:30 PM as the contractor works along the ramps and 4th Street. Motorists are advised to reduce speed in the work zone and watch for flaggers assisting with traffic control
[Stansell Electric Company, Inc./Chattanooga East/CNY900]

HAMILTON COUNTY I-75 at I-24 Interchange Reconstruction Phase 2: Nightly Lane closures will regularly occur on this project, 9 PM to 6 AM, on I-75 North and South between Exit 1 (East Ridge) and Exit 3A (East Brainerd Road/ SR-320) and on I-24 East and West from Germantown Road to Spring Creek Road, MM182 to MM185, for various construction activities. These closures may temporarily reduce traffic to a single lane. Uniformed police officers will be present in these work zones to assist with traffic management and to enforce traffic laws. Nighttime lane closures from 8 PM to 6 AM are scheduled on I-24 East and West between Germantown Road and through the I-75 interchange for placement of permanent thermoplastic pavement markings, shoulder rumble strips and to work on various punch list items. This night work will continue weekly from Sunday through Thursday during the month of February. The contractor will have daytime lane closures (9 AM to 3 PM) on North and South Terrace for various pavement repairs, milling and final pavement. This work is scheduled to take place Monday through Friday, weather permitting, and will occur weekly through February until completed. As this work on North and South Terrace progresses it will be necessary to temporarily close exit and entrance ramps from I-24 so that crews can safely pave these areas. Paving crews are currently working on North Terrace, the exit ramp (Exit 184) from I-24 West between McBrien Road and South Moore Road is scheduled for temporary closure (9 AM to 3 PM) on Tuesday (2/10) and Wednesday (2/11) weather permitting. Once the paving in this area is complete, they will move to South Terrace and the exit and entrance ramps between Belvoir Avenue and South Moore Road are scheduled for closure on Thursday (2/12) and Friday (2/13). The entrance ramp from South Terrace between South Moore Road and McBrien Road will close the first part of next week (2/16 through 2/20) to continue this paving. Other short-term, temporary ramp closures may be needed in the future to complete small areas (i.e. ramp gore areas, shoulders, lane transitions, etc.) skipped during the normal full width paving of the travel lanes. Message boards, signs and detours will be provided to warn motorists of these closures and to guide them to the next available exit or entrance ramp. The contractor plans to begin working on shifting and opening all lanes on I-75 South and North in their final alignment starting next week from Sunday (2/15) through Thursday (2/19). The first work will occur on I-75 South from the East Brainerd Road interchange (MM 3) to south of the bridge over the CSX railroad (MM 2). There will be nighttime lane closures (9 PM to 6 AM) on I-75 South and during some of these nights the entrance ramp from East Brainerd Road to I-75 South will have to be temporarily closed to safely remove conflicting lane lines and establish the new final traffic lane alignment. Message boards, signs and detours will be provided to warn motorists of these closures and to guide them to an available entrance ramp to I-75 South. Once the traffic shifts on I-75 South are complete then the contractor will move to I-75 North and work on realigning and opening these lanes. To fully transition all traffic lanes on I-75 South and North is anticipated to take several weeks of nighttime closures to complete. Most of the remaining work items on this project are temperature and weather sensitive. If any of them are canceled due to inclement conditions, they will be rescheduled to take place on the next available day and time when adequate conditions exist. It may also be necessary to do short duration (15 to 30 minutes) rolling roadblocks during the day or night for patching potholes, clearing debris or repairing guardrail, attenuators, etc.
[Wright Brothers Construction Company, Inc./Maj Prj – Blevins/DB2101]

HAMILTON COUNTY I-75 at the Hamilton Place Mall interchange: The SR-153 southbound ramp to I-75 northbound has been reduced to one lane. Traffic shifts have been implemented on northbound I-75, Shallowford Road entrance ramps, and Shallowford Road exit ramps and the Hamilton Place Mall exit ramp. Hamilton Loop Road is closed for retaining wall construction and storm drainage installation between the intersections near Markman’s Jewelers and Texas Roadhouse. Beginning at 4 AM on 02/14/26 through 6 AM on 02/16/26 the I-75 NB Exit 5 Ramp to Shallowford Road will be closed for bridge girder erection. There will be a detour in place, which will route I-75 NB traffic to Volkswagen Drive to I-75 SB for access to Exit 5. The speed limit has been reduced on I-75 throughout the project limits. Nightly lane closures are permitted 8 PM to 6 AM. Motorists should use caution, paying attention to construction signage and watching for construction vehicles and personnel. [Summers-Taylor, Inc./Chattanooga West/CNX358]

HAMILTON COUNTY SR-153 (STATE HWY. 153) Utility Work in both directions at LM 10.24: Flagging-assisted lane closures on SR-153 between Carmack Dr. and Sutton Drive. Motorists should reduce speed and be prepared to stop. Trucks, signage, flaggers, and barrels/cones will be present, 02/12/2026 through 02/18/2026 from 9 am – 2 pm (2025-993)

HAMILTON COUNTY SR-17 (ST. ELMO AVE.) Utility Work both directions at LM .74: Flagging-assisted lane closures on SR 17 (St. Elmo Hwy) between 51st St and 49th Ave. Motorists should reduce speed and be prepared to stop. Trucks, signage, flaggers, and barrels/cones will be present, 01/15/2026 through 02/18/2026 from 9 AM to 2 PM [2025-696]

HAMILTON COUNTY SR-17 (ST. ELMO AVE.) Utility Work both directions from LM 1.12 to LM 1.77: Flagging-assisted lane closures on SR-17 (St. Elmo Ave.) between Tennessee Ave. and W 45th St. Motorists should reduce speed and be prepared to stop. Trucks, signage, flaggers, and barrels/cones will be present, 01/29/2026 to 02/18/2026 from 9 am – 2 pm [2025-905)

HAMILTON COUNTY SR-2 (BRAINERD RD.) Utility Work both directions at LM 5.92: Flagger-assisted lane closures on SR-2 (Broad St.) between Tennessee and 37th Avenue. Motorists should reduce speed and be prepared to stop. Trucks, arrow board/message boards, flaggers, and barrels/cones will be present, 02/12/2026 through 02/18/2026 from 9 pm to 5 am [2024-768]

HAMILTON COUNTY SR-2 (BROAD ST.) Utility Work both directions from LM 6.17 to LM 6.66: Flagging-assisted lane closures on SR-41 (Broad St.) between Williams St. and St. Elmo Ave. Motorists should reduce speed and be prepared to stop. Trucks, signage, flaggers, and barrels/cones will be present, 01/29/2026 to 02/18/2026 from 9 am – 2 pm [2025-907)

HAMILTON COUNTY SR-2 (CUMMINGS HWY.) Utility Work both directions from LM .67 to LM .70: Flagging-assisted lane closures on SR-002 (Cummings HWY.) between Kelly’s Ferry Rd and W. Hills Dr. Motorists should reduce speed and be prepared to stop. Trucks, signage, flaggers, and barrels/cones will be present, 02/09/2026 through 02/13/2026 from 9 am – 2 pm [2025-1007)

HAMILTON COUNTY SR-2 (CUMMINGS HWY.) Utility Work both directions from LM .69 to LM .79: Flagging-assisted lane closures on SR-2 (Cummings HWY) between Hills Dr and 4347 Cummings HWY. Motorists should reduce speed and be prepared to stop. Trucks, signage, flaggers, and barrels/cones will be present, 01/22/2026 through 02/18/26 from 9 am – 2 pm [2025-648]

HAMILTON COUNTY SR-2 (DODDS AVE.) Utility Work both directions from LM 10.36 to LM 10.60: Flagging assisted lane closures on SR-2 (Dodds Ave.) Between 14th St and 19th St. Motorists should reduce speed and be prepared to stop. Trucks, signage, flaggers, and barrels/cones will be present, 02/16/2026 through 02/18/2026 from 9 am – 2 pm (2026-068)

HAMILTON COUNTY SR-2 (LEE HWY.) Utility Work both directions from LM 18.80 to LM 18.86: Flagger-assisted lane closures on SR-2 (Lee Hwy) between McCutcheon Rd and Elm Dr. Motorists should reduce speed and be prepared to stop. Trucks, arrow board/message boards, flaggers, and barrels/cones will be present, 10/2/25 to 02/28/2026 from 9 am – 2 pm. [2024-338]

HAMILTON COUNTY SR-27 [5.51-7.93] from I-24 to Georgia State Line resurfacing on US-27:
[APAC – Atlantic, Inc./Chattanooga East/CNZ184]

HAMILTON COUNTY SR-29 [20.72-25.756] from SR-111 to Old Dayton Pk. Resurfacing: The contractor is resurfacing US-27, requiring temporary lane closures throughout the project length. The contractor’s schedule is 7 AM to 7 PM and weather-dependent. Some work maybe completed at night to facilitate the project schedule. [Rogers Group, Inc./Chattanooga West/CNZ034]

HAMILTON COUNTY SR-312 (BIRCHWOOD PK.) Utility Work both directions at LM .37: Flagging-assisted lane closures on SR-312 (Birchwood Pike) before the Hwy 60 exchange. Motorists should reduce speed and be prepared to stop. Trucks, signage, flaggers, and barrels/cones will be present, 02/12/2026 from 9 am – 2 pm (2026-003)

HAMILTON COUNTY SR-320 (E. BRAINERD RD.) Utility Work both directions from LM .54 to LM .59: Flagging-assisted lane closures on SR-320 (East Brainard Rd.) Between Bass Rd and Benham Rd. Motorists should reduce speed and be prepared to stop. Trucks, signage, flaggers, and barrels/cones will be present, 02/12/2026 from 9 am – 2 pm (2026-026)

HAMILTON COUNTY SR-320 (E. BRAINERD RD.) Utility Work both directions from LM .92 to LM 1.36: Flagging-assisted lane closures on SR-320 (East Brainard Rd.) between Glenbury Court and Benham Dr. Motorists should reduce speed and be prepared to stop. Trucks, signage, flaggers, and barrels/cones will be present, 01/29/2026 to 02/12/2026 from 9 am – 2 pm [2025-901)

HAMILTON COUNTY SR-58 (HWY. 58) Utility Work both directions from LM 1.66 to LM 2.16: Flagging-assisted lane closures on SR-58 (Hwy 58) between Everett St. and St. Elmo Ave. Motorists should reduce speed and be prepared to stop. Trucks, signage, flaggers, and barrels/cones will be present, 01/29/2026 to 02/18/2026 from 9 am – 2 pm [2025-906)

HAMILTON COUNTY SR-58 (HWY. 58) Utility Work both directions from LM 16.70 to LM 17.08: Flagging-assisted lane closures on SR-58 (Hwy 58) between Crowes Nest Dr and Sims rd. Motorists should reduce speed and be prepared to stop. Trucks, signage, flaggers, and barrels/cones will be present, 02/17/2026 from 9 am – 2 pm with a rain date of 02/20/2026 [2025-1017)

JACKSON COUNTY SR-135 (DODSON BRANCH HWY.) TDOT Maintenance northbound from LM 11.8 to LM 12.0: SR135 will be reduced to one lane due to a soil nail project starting 2/5/26 until the project is completed. Traffic signals are in place. Motorists are encouraged to slow down and use caution when in the area.

MARION COUNTY SR-108 [2.8-3.24] slide mitigation: The contractor will be performing slide mitigation operations, including grading, drainage and paving on SR-108 in Marion County at LM 2.8. The roadway will be reduced to one lane controlled by temporary traffic signals. The project completion date is 08/31/2027. Please use caution when driving through the work zone.
[Wright Brothers Construction Company, Inc./Dunlap/CNZ226]

MARION COUNTY SR-150 (US-41) Utility Work both directions from LM .28 to LM .43: Flagging-assisted lane closures on SR-150 (Hwy 41) in front of the jasper middle school. Motorists should reduce speed and be prepared to stop. Trucks, signage, flaggers, and barrels/cones will be present, 02/12/2026 from 9 am – 2 pm (2025-989)

MARION COUNTY SR-2 [17.2-17.3] from 17.2 to 17.3 construction: The contractor will be performing grading and drainage operations on SR-2 in Marion County near LM 17.25. This work will require a lane shift for the EB traffic, the WB traffic will be unaffected. Please slow down and use caution when driving through the work zone. [Talley Construction Company, Inc./Dunlap/CNZ244]

MCMINN COUNTY I-75 [0-2.06] from MM 35 (Bradley County Line) to MM 37 resurfacing: The contractor will continue paving operations. This work will require temporary lane closures in both directions, which will occur Sunday nights through Friday nights 8 PM to 6 AM. Motorists should exercise caution and pay attention to construction signage. The speed limit will be reduced during paving operations. [Wright Brothers Construction Company, Inc./Chattanooga West/CNY261]

MCMINN COUNTY I-75 [2.06-4.32] from MM 37 to MM 39.5 resurfacing: The contractor will continue paving operations. This work will require temporary lane closures in both directions, which will occur Sunday nights through Friday nights 8 PM to 6 AM. Motorists should exercise caution and pay attention to construction signage. The speed limit will be reduced during paving operations.
[Wright Brothers Construction Company, Inc./Chattanooga West/CNZ109]

MCMINN COUNTY SR-39 construction of a bridge over Middle Creek (LM 13.4): During this reporting period, the contractor will be flagging the roadway to perform work. This flagging operation will only occur during daytime hours.
[Whaley Construction, LLC/Chattanooga East/CNX069]

OVERTON COUNTY SR-111 (BYRDSTOWN HWY.) Utility Work both directions from LM 14.74 to LM 15.95: Flagging-assisted lane closures on SR-111 (Byrdtown Highway) at 1747 Byrdtown Highway. Motorists should reduce speed and be prepared to stop. Trucks, signage, flaggers, and barrels/cones will be present, 02/12/2026 through 02/18/2026 from 9 am – 2 pm (2026-031)

OVERTON COUNTY SR-111 (BYRDSTOWN HWY.) Utility Work both directions from LM 15.95 to LM 17.52: Flagging-assisted lane closures on SR-52 (Byrdstown Hwy) Between Garnet Mill Rd and Big Springs Rd. Motorists should reduce speed and be prepared to stop. Trucks, signage, flaggers, and barrels/cones will be present, 02/16/2026 through 02/27/2026 from 9 am – 2 pm (2026-033)

OVERTON COUNTY SR-111 (BYRDSTOWN HWY.) Utility Work both directions from LM 17.52 to LM 19.47: Flagging-assisted lane closures on SR-52 (Byrdstown Hwy) Between Big Springs Rd. and Wildwood Lane. Motorists should reduce speed and be prepared to stop. Trucks, signage, flaggers, and barrels/cones will be present, 02/16/2026 through 02/27/2026 from 9 am – 2 pm (2026-035)

OVERTON COUNTY SR-111 (BYRDSTOWN HWY.) Utility Work both directions from LM 19.46 to LM 21.01: Flagging-assisted lane closures on SR-52 (Byrdstown Hwy) Between Big Springs Rd. and Eastport Dock Rd. Motorists should reduce speed and be prepared to stop. Trucks, signage, flaggers, and barrels/cones will be present, 02/16/2026 through 02/27/2026 from 9 am – 2 pm (2026-037)

OVERTON COUNTY SR-294 (E. MAIN ST.) Utility Work both directions from LM .0 to LM 14.72: Flagging-assisted lane closures on SR-294 (East Main St.) Between School Mountain rd. and Linder Mountain rd. Motorists should reduce speed and be prepared to stop. Trucks, signage, flaggers, and barrels/cones will be present, 02/16/2026 through 02/27/2026 from 9 am – 2 pm (2026-029)

OVERTON COUNTY SR-52 (E. MAIN ST.) Utility Work both directions from LM 11.24 to LM 11.28: Flagging-assisted lane closures on SR-52 (East Main St.) Between North Church St. and Myers St Motorists should reduce speed and be prepared to stop. Trucks, signage, flaggers, and barrels/cones will be present, 02/16/2026 through 02/27/2026 from 9 am – 2 pm (2026-027)

OVERTON COUNTY SR-52 (E. MAIN ST.) Utility Work both directions from LM 11.45 to LM 12.12: Flagging-assisted lane closures on SR-52 (East Main St.) Between Oak St. and W. Main St. Motorists should reduce speed and be prepared to stop. Trucks, signage, flaggers, and barrels/cones will be present, 02/16/2026 through 02/27/2026 from 9 am – 2 pm (2026-029)

OVERTON COUNTY SR-85 (HILHAM HWY.) Utility Work both directions from LM 10.13 to LM 11.10: Flagging-assisted lane closures on SR-85 (Hilham HWY) Between Windle Community Rd and Hawkins Rd. Motorists should reduce speed and be prepared to stop. Trucks, signage, flaggers, and barrels/cones will be present, 02/18/2026 through 02/22/2026 from 9 am – 2 pm (2025-471)

POLK COUNTY SR-33 (HWY. 411) Utility Work both directions from LM 2.83 to LM 5.35: Flagger-assisted lane closures on SR-33 (411 Hwy) between Ridge Rd and Waters Rd. Motorists should reduce speed and be prepared to stop. Trucks, arrow board/message boards, flaggers, and barrels/cones will be present, 01/12/2026 through 02/13/26 from 8 am – 3 pm. [2023-855]

POLK COUNTY SR-68 over SR-40 the construction of bridges: During this reporting period, the contractor will begin construction on the SR-68 South bridge. All SR-68 traffic will use the newly constructed SR-68 North bridge while construction occurs on the new SR-68 South bridge. All SR-40/SR-68 interchange traffic will utilize the SR-68 North interchange ramps. A temporary 3-way stop has been implemented at the intersection of the SR-40 interchange ramp and SR-68. Motorists are encouraged to slow down when entering the construction zone and look out for new stop signs on SR-68 near the SR-40/SR-68 interchange.
[Wright Brothers Construction Company, Inc./Cleveland/CNZ042]

PUTNAM COUNTY I-40 [303.6-304.2] from MM 303.6 to MM 304.2 bridge repair and resurfacing: The contractor has started working on the bridge repair on I-40 at MM 304.6. Motorists should use caution in the area. [Rogers Group, Inc./Crossville/CNZ290]

PUTNAM COUNTY SR-136 construction from north of the SR-111 interchange to south of the I-40 interchange: The contractor will continue normal working activities throughout the project limits. During this work, temporary lane closures are possible, and flaggers will be present. Motorists are encouraged to use caution while traveling through the work zone and should be aware of construction equipment adjacent to the roadway. [Rogers Group, Inc./Cookeville/CNV284]

PUTNAM COUNTY SR-24 (CROSSVILLE HWY.) Utility Work both directions from LM 35.55 to LM 38.09: Eastbound and Westbound Lane closures on SR-24 (Crossville Hwy.) between E. Wilder Ave. and Walker Farm Rd. Motorists should reduce speed and be prepared to stop. Arrow board/message boards, flaggers, and barrels/cones will be present, 11/06/25 through 05/06/2026 from 9 am – 2 pm. [2025-521]

REGION 2 Dynamic Message Sign (DMS) Life Cycle Replacement: No lane closures this week.
[Davis H. Elliot Construction Company, Inc./Chattanooga East/CNX413]

REGION 2 The on-call cable barrier repair on various Interstate and State Routes.: The contractor will have short term shoulder and/or lane closures in order to perform cable barrier rail repair. These closures will take place daily Monday through Friday during daylight hours on the interstates and some major divided highway state routes. There many also be nightly Sunday through Thursday from 7 PM to 6 AM, rarely and only as needed. At least one travel lane will remain open to traffic at all times. Typically, only a shoulder closure will be used in the median, but lane closures will be employed as needed.
[LU, Inc./McMinnville/CNZ205]

REGION 2 The on-call guardrail repair and new guardrail installation on various Interstate and State Routes: The contractor will have short term shoulder and/or lane closures in order to perform guardrail repair. These closures will take place on the interstate nightly Sunday through Thursday from 7 PM to 6 AM and daily Monday through Friday on state routes. At least one travel lane will remain open to traffic at all times on the interstate, and flaggers will be present on state routes during any work that is performed.
[Reynolds Fence and Guardrail, Inc./McMinnville/CNZ112]

REGION 2 The sweeping on various Interstate and State Routes: Sweeping operations are planned throughout Region 2 this reporting period. Sweeping operations are mobile operations along the inside and outside shoulders with impacts to adjacent traffic lanes. These operations will occur at night between 8 PM and 6 AM for interstates and high traffic state routes, while daytime sweeping can be anticipated between 9 AM to 3 PM for lower traffic state routes.
[Sweeping Corporation of America, Inc./Chattanooga West/CNY210]

REGION 2 Various Interstate and SRs – Cable Barrier Repair: The contractor will have short term shoulder and/or lane closures in order to perform cable barrier rail repair for punch list operations. These closures will take place on the interstate nightly Sunday through Thursday from 7 PM to 6 AM as needed and daily Monday through Friday. At least one travel lane will remain open to traffic at all times. Typically, only a shoulder closure will be used in the median, but lane closures will be employed as needed. [LU, Inc./McMinnville/CNY183]

RHEA COUNTY SR-30 (DAYTON MTN. HWY.) Utility Work both directions from LM .13 to LM 2.22: Flagging-assisted lane closures on SR-30 (Dayton Mtn HWY) Between Walker Rd. and Tigues Creek Rd. Motorists should reduce speed and be prepared to stop. Trucks, signage, flaggers, and barrels/cones will be present, 01/12/2026 through 02/27/2026 from 9 am – 2 pm [2025-725]

WHITE COUNTY SR-111 [15.25-16.25] from O’Connor Rd to Old Kentucky Rd culvert replacement: The left lane of both the Northbound and Southbound side of SR-111 will be closed until further notice. At this time the contractor will be constructing median crossovers to allow for later work to be completed. Motorists are encouraged to use caution as they approach the work zone, and they should be prepared to stop. Motorists should also be aware of the speed limit reduction in place and follow all signs displayed.
[Rogers Group, Inc./Cookeville/CNZ902]

 

RESTRICTIONS

CAMPBELL, COFFEE, DAVIDSON, DICKSON, GILES, GREENE, HAYWOOD, KNOX, MCMINN, SHELBY, AND WILLIAMSON COUNTY – CNX913:

CUMBERLAND COUNTY – CNZ206: Both lanes of SR-24 are closed at LM 15.06 to LM 15.6