ROADWAY ACTIVITY REPORT FOR EAST TENNESSEE (JUNE 12 – 18)
CLAY COUNTY SR-52 [18.7-20.56] from South of Boyd Street to Near SR-53 resurfacing: The contractor has begun resurfacing operations. Nightly lane closures will be used along with flaggers as needed to control traffic through the work zone between 7 pm and 6 am. [Rogers Group, Inc./Livingston/CNZ023]
CLAY, CUMBERLAND, DEKALB, PICKETT, PUTNAM, AND WHITE COUNTY The ADA curb ramp upgrades on various State Routes: The contractor will be removing and replacing curb ramps in White County along SR-289 from LM 0.00 – 2.61 and in Pickett County along SR-325 from LM 4.23 – 8.08. During this work, sidewalk closures will be in place and lane closures will be used to facilitate the work. Flaggers will be present to control the flow of traffic through the work zone. Motorists are encouraged to use caution through the work zone and should be prepared to stop.
[MarCor Construction, Inc./Cookeville/CNY252]
CUMBERLAND COUNTY I-40 Utility Work both directions from MM 304.4 to MM 311: Officer assisted rolling roadblock on I-40 beginning eastbound in Putnam County LM 299.6 (near Exit 300 Monterey/Livingston) and westbound in Cumberland County at LM 310.2 (near Exit 311 Plateau Road). Message boards, signage, trucks, and law enforcement vehicles will be preset along I-40 and ramps. Motorists should be prepared to stop and expect delays. 06/15/25 from 6 am to 8 am, with rain date of 06/22/25. [PIN 105727.01 – Utilities Office]
CUMBERLAND COUNTY SR-28 (US-127) bridge construction and paving from north of I-40 (LM 17.8) to near Potato Farm Road (LM 22.7): The contractor continues grading activities throughout the project limits. Temporary lane closures and/or periodic traffic stoppages will be necessary for construction activities. Hubert Conley Road at the intersection of SR-28 has been closed for construction activities. The contractor has closed North Grace Hill Drive at the existing intersection of SR-28 (US-127) for construction activities. Motorists should utilize South Grace Hill Drive as the detour with appropriate signs. Traffic has been moved to temporary alignment on Plateau Road and permanent alignment on Potato Farm Road. Flaggers and advanced warning signs will accompany any closures. Motorists should use caution when traveling through the work zone as traffic patterns change. [Jones Bros. Contractors, LLC/Crossville/CNV009]
CUMBERLAND COUNTY SR-28 (US-127 S.) Utility Work both directions from LM 28 to LM 29: Flagger assisted lane closures on SR-28 (US-127 S) at the intersection with Bear Creek Road / Beaty Road. Motorists should reduce speed and be prepared to stop. Trucks, arrow board/message boards, flaggers, and barrels/cones will be present, 06/12/25 from 9 am – 12 pm, with a rain date of 06/13/25. [2025-259]
CUMBERLAND COUNTY SR-1 (US-70) construction of bridge over the Obed River (LM 12.7): Construction activities continue on SR-1 (US-70) over the Obed River bridge. SR-1 has been reopened. Construction crews will be working outside of the roadway to install utilities. Traffic should be cautious of construction equipment near the shoulders. Contractor may need to flag traffic to move equipment or vehicles across the road.
[Whaley Construction, LLC/Crossville/CNX110]
CUMBERLAND COUNTY SR-1 [8.86-13.27] from Pomona Road to SR-24 resurfacing: The contractor anticipates starting resurfacing operations on SR-1 from near Pomona Road to SR-24 intersection starting 06/12/25. The contractor will utilize temporary lane closures and flaggers throughout the project. Signs will accompany any closures. Motorists should use caution when traveling through the work zone. [Rogers Group, Inc./Crossville/CNZ067]
CUMBERLAND COUNTY SR-28 (Main Street, US-127) downtown pedestrian improvement project between Lantana Road (Highway 70 East) and Neecham Street: Construction activities are ongoing along SR-28 (Main Street). The contractor is working on removing and replacing the concrete sidewalk and curb ramps from Lantana Road to West 2nd Street. The contractor will be pouring concrete beginning from Lantana Road to West 2nd Street. During this time, the contractor will utilize flaggers, and the road will be reduced to one lane for a period of time. Once operations are completed for the day, traffic will be reopened to two lanes. The shoulder parking along this area has been closed. Signs and flaggers may be utilized during these lane closures and/or lane shifts. Motorists should use caution when traveling through the work zone. [Adams Contracting, LLC/Crossville/LP24_1]
CUMBERLAND COUNTY SR-298 [8.35-9.02] from north of Catoosa Canyon Dr to south of Obed Pines Rd construction of a small drainage structure: The contractor continues construction activities on Genesis Road (SR-298). Both lanes of Genesis Road (SR-298) at LM 8.35 to LM 9.02 have been closed and will be closed for the duration of the project with a posted detour route along SR-28 (US-127) and SR-62. The contractor will be working to replace a culvert underneath Genesis Road and installing retaining walls. RESTRICTIONS: Both lanes of Genesis Road (SR-298) are closed from LM 8.35 to LM 9.02. [J. Hill Excavating, LLC/Crossville/CNZ103]
CUMBERLAND COUNTY SR-462 from SR-28 (US-127N / LM 3.1) to SR-298 (Genesis Road / LM 4.6) in Crossville: Construction activities are in progress. Contractor anticipates opening the roadway to all lanes of traffic. Motorists should be cautious of the change in traffic. Activities may require temporary lane closures and/or traffic stoppages on Interstate Drive (SR-462), as well as short term closures of city streets. Flagging operations will accompany these closures with appropriate signs. Traffic has been shifted to the center lanes along Interstate Drive (SR-462). Motorists traveling west on Interstate Drive should be mindful of the “Right Turn Only” lane at the intersection of Stout Drive. Motorists should use caution when traveling through the work zone. [Rogers Group, Inc./Crossville/CNV010]
CUMBERLAND AND FENTRESS COUNTY SR-28 (US-127) widening from near N. Lowe Rd (LM 29.2) to north of SR-62 (LM 1.9): The contractor will continue work along the new alignment of SR 28. Flaggers are being intermittently used to control traffic through parts of the work zone. Motorists are encouraged to use caution and watch for construction equipment and personnel adjacent to the roadway. [Jones Bros. Contractors, LLC/Cookeville/CNV300]
DEKALB COUNTY SR-26 (SPARTA HWY.) Utility Work both directions from LM 26 to LM 29.75: Flagger assisted lane closures on SR-26 (Sparta Hwy) from the White County line to Billings Road / Johnson Chapel Road. Motorists should reduce speed and be prepared to stop. Trucks, arrow board/message boards, flaggers, and barrels/cones will be present, 05/28/25 thru 08/30/25 from 8 am – 3 pm. [2024-410]
DEKALB COUNTY SR-264 (TEMPERANCE HALL RD.) TDOT Maintenance northbound from LM 0.0 to LM 1.00: SR264 will be reduced to one lane from 6/12/25 thru 6/18/25 to repair a slide area near the 0.54MM. Traffic signals will be in place. Motorists are encouraged to slow down and use caution when in the area.
DEKALB COUNTY SR-26 (US-70) grading, drainage, and construction of retaining walls and paving from near SR-53 (LM 2) to near SR-96 (LM 6.1): The contractor continues grading and construction activities throughout the project. Temporary lane closures and periodic traffic stoppages will be necessary for construction activities and motorists should be prepared to stop while traveling through the work zone. Motorists are encouraged to obey posted speed limit and to watch for construction equipment and personnel adjacent to the roadway. The West end of Old Liberty Road will be closed to through traffic due to construction activities. Motorists and EMS will need to use the East entrance of Old Liberty Road to gain access and follow detour signs. [Twin K Construction/Cookeville/CNV012]
JACKSON COUNTY SR-262 (GLADDICE HWY.) TDOT Bridge Inspection westbound at LM 7.56: On Wednesday, June 18th, a routine and in-depth inspection of the Frank G. Clement bridge, which carries SR262 over the Cumberland River in Jackson County, will require the westbound lane to be closed from 8:30 AM until 3:30 PM. Flaggers will be present to direct traffic through the work zone. Motorists are advised to slow down and be prepared to stop as the approach the bridge from either direction. Be alert for flaggers and obey all temporary traffic control.
OVERTON COUNTY SR-52 resurfacing from east of SR-294 (LM 12.2) to near Dogwalk Road (LM 18.3): The contractor has completed resurfacing. Intermittent lane closures will be used along with flaggers to control traffic through the work zone as the contractor completes the remaining incidental work. Motorists are encouraged to use caution and watch for construction equipment and personnel. [Rogers Group, Inc./Livingston/CNZ039]
OVERTON COUNTY SR-52 [10.96-11.28] from Near Henson St. to Robert St. Resurfacing: The contractor has completed resurfacing operations. Intermittent lane closures will be used along with flaggers as needed to control traffic through the work zone. Motorists are encouraged to use caution and watch for construction equipment and personnel.
[Rogers Group, Inc./Livingston/CNZ039]
OVERTON COUNTY SR-85 [11.17-11.91] from SR-111 to SR-52 resurfacing: The contractor has completed resurfacing operations. Intermittent lane closures will be used along with flaggers as needed to control traffic through the work zone. Motorists are encouraged to use caution and watch for construction equipment and personnel. [Rogers Group, Inc./Livingston/CNZ039]
PICKETT COUNTY SR-111 (HWY. ONE ELEVEN) TDOT Bridge Inspection southbound at LM 3.21: On Tuesday, June 17th, TDOT consultants will perform an evaluation of the L. B. Hassler Memorial Bridge over the Obed River in Pickett County. This work will require closure of the south-bound shoulder on the bridge from 8:30 AM until 3:30 PM.
PUTNAM COUNTY I-40 TDOT Contractor eastbound from MM 273 to MM 276: I-40 will have the right shoulder closed from exit 273-276 eastbound for a tree cutting operation that will continue 6/5/25-6/13/25 from 8AM to 5PM each day until work is completed. Message boards will be in place. Motorists are encouraged to slow down and use caution when in the area and be alert for trucks entering the roadway.
PUTNAM COUNTY I-40 TDOT Maintenance eastbound from MM 301.5 to MM 302.0: I-40 will be reduced to one lane eastbound on 6/12/25 from 8AM-2PM from the 301.5-302 to grout a slip liner. Motorists are encouraged to slow down and use caution when in the area.
PUTNAM COUNTY SR-136 construction from north of the SR-111 interchange to south of the I-40 interchange: The contractor continues grading activities throughout the project. Temporary lane closures and/or periodic traffic stoppages will be necessary for construction activities. West Davis Road and Henley Drive remain closed at the intersection of SR-136 with detour signs to utilize Bunker Hill Road. Motorists are encouraged to use caution while traveling through the work zone and be aware of construction personnel. [Rogers Group, Inc./Cookeville/CNV284]
PUTNAM COUNTY SR-136 (S. JEFFERSON AVE.) Utility Work southbound from LM 2.55 to LM 2.75: Southbound lane closures on SR-136 (S Jefferson Ave) between Spring Street Town Square to I-40. Motorists should reduce speed and be prepared to stop. Arrow board/message boards, flaggers, and barrels/cones will be present, 11/14/24 through 07/30/25 from 9 am – 2 pm. [2024-640]
PUTNAM COUNTY SR-84 (CALFKILLER HWY.) TDOT Maintenance northbound from LM 3.0 to LM 4.0: SR84 will be reduced to one lane from 6/10/25 thru 6/30/25 to repair a slide area near the 3.2MM. Signals will be installed. Motorists are encouraged to slow down and use caution when in the area. RESTRICTIONS: Horizontal clearance will be restricted to 9FT. NO TRACTOR TRAILERS.
PUTNAM COUNTY SR-84 (CALFKILLER HWY.) Utility Work both directions from LM 1 to LM 8: Flagger assisted lane closures on SR-84 (Calfkiller Hwy) from the White County line to Hidden Acres Road. Motorists should reduce speed and be prepared to stop. Trucks, arrow board/message boards, flaggers, and barrels/cones will be present, 04/24/25 thru 07/30/25 from 8 am – 3 pm. [2023-577]
PUTNAM COUNTY SR-24 [23.27-29.89] from Hitchcock Drive to Mill Creek Road Resurfacing: The contractor will be continuing milling and paving operations. During this work, lane closures will be utilized with one lane shut down. Flaggers will be present to control the flow of traffic through the work zone. Motorists are encouraged to use caution as they approach the work zone, and they should be prepared to stop. [Rogers Group, Inc./Cookeville/CNZ041]
WHITE COUNTY SR-26 (SMITHVILLE HWY.) Utility Work both directions from LM 0 to LM 1: Flagger assisted lane closures on SR-26 (Sparta Hwy) from the DeKalb County line to Jay Hutchings Road. Motorists should reduce speed and be prepared to stop. Trucks, arrow board/message boards, flaggers, and barrels/cones will be present, 05/28/25 thru 08/30/25 from 8 am – 3 pm. [2024-410]
DISTRICT 28
BLEDSOE COUNTY SR-30 and SR-443, the grading, drainage, stream relocation, widening, and resurfacing on Summer City Road: The contractor will be performing grade work and widening on Summer City Road in Bledsoe County. This work will narrow the lanes at LM 2.0 and LM 4.3 and will leave both lanes open to traffic. Please slow down and use caution when driving through the work zone. [Rogers Group, Inc./Dunlap/CNY153]
COFFEE COUNTY I-24 (MM 117) construction of an overpass carrying Wattendorf Memorial Highway/AEDC Road, including grading, drainage, retaining walls, and paving: There will be a right lane closures on I-24 WB on 6/17 from 7PM to 6AM to install traffic control devices. Also, on 6/17 from 7PM to 6AM, there will also be a short duration ramp closure on I-24 EB Exit ramp and MM 117 to remove guardrail. [Jones Bros. Contractors, LLC/Tullahoma/CNZ029]
COFFEE COUNTY I-24 (MM 105) construction of an overpass carrying SR-2 (US-41): Phase 2 of I-24 bridge replacement at Exit 105 will continue this week. SR-2 will be reduced to one lane utilizing traffic signal system. The temporary traffic signal will remain in effect until 10/16/25. There will be left lane closures on I-24 EB and WB on 6/17 and 6/18 from 7PM to 5AM to facilitate the phase 2 concrete deck pour. One lane in each direction will be maintained at all times.
[Bell and Associates Construction, LP/Tullahoma/CNX309]
COFFEE COUNTY SR-55 construction from First Avenue (LM 2.0) to SR-16 (US-41A, N. Jackson St, LM 2.6) in Tullahoma: Phase 1 of roadway widening and bridge replacement on SR-55 (Wilson Ave.) will continue this week. Contractor may use temporary lane shifts to complete utility work. Phase 1 traffic shift has reduced lanes from 3 to 2 from Cedar Lane to near Grau Lane in order to continue bridge replacement and storm drainage work.
[Dement Construction Company, LLC/Tullahoma/CNX912]
COFFEE COUNTY SR-55 repair of the bridge over the Little Duck River (LM 14.0): Lanes are reduced to one lane in each direction across the SR-55 bridge over the Little Duck River for bridge repair work. This lane reduction will be in place until work is complete in Fall 2025. [Mid-State Construction Company, Inc./Tullahoma/CNX412]
COFFEE COUNTY SR-55 [13.79-15.32] from US-41 to north of Interstate Drive resurfacing: There will be no lane closures during Bonnaroo. Lane closures for final pavement markings will resume Tuesday 6/17 and will continue nightly until complete from 7PM to 6AM. One lane in each direction will be maintained at all times. [Volunteer Paving, LLC/Tullahoma/CNY267]
FRANKLIN COUNTY SR-130 (OLD TULLAHOMA RD.) Utility Work both directions from LM 3 to LM 5: Flagger assisted lane closures on SR-130 (Old Tullahoma Road) at the intersection with Hurricane Road / Blue Creek Road. Motorists should reduce speed and be prepared to stop. Trucks, arrow board/message boards, flaggers, and barrels/cones will be present, 06/16/25 thru 06/30/25 from 9 am – 2 pm. [2025-180]
FRANKLIN COUNTY SR-433 (VETERANS MEMORIAL DR.) Utility Work both directions from LM 5 to LM 6: Multi-lane closures on SR-433 (Veterans Memorial Drive) between Cowan Hwy / 41A and Nissan Powertrain Drive. Motorists should reduce speed and be prepared to stop if needed. Trucks, arrow board/message boards, and personnel will be present, 06/02/25 thru 06/13/25 from 9 am – 2 pm. [2025-260]
FRANKLIN COUNTY Old Decherd Road over Wagner Creek (LM 0.3) construction of a bridge: Old Decherd Road is closed at Wagner Creek for bridge replacement. A signed detour is in place. The road closure will be in place for the duration of the project through June 30th, 2025. RESTRICTIONS: Old Decherd Road at Wagner Creek is closed.
[Dement Construction Company, LLC/Tullahoma/CNY068]
MARION COUNTY SR-2 (US-HWY. 41) Utility Work both directions from LM 32 to LM 34: Flagger assisted lane closures on SR-2 (US Hwy 41) in front of Kelly’s Ferry Church of God west of Raccoon Mountain Drive. Motorists should reduce speed and be prepared to stop. Trucks, arrow board/message boards, flaggers, and barrels/cones will be present, 06/18/25 thru 06/30/25 from 9 am – 2 pm. [2025-053]
MARION COUNTY SR-156 repair of bridge over Tennessee River, LM 15.2: The contractor will be performing painting operations and structural repairs on the SR-156 bridge over the Tennessee River in South Pittsburg. This work will require a traffic shift leaving both lanes open to traffic. Please use caution when driving through the work zone.
[Olympus Painting Contractors Inc./Dunlap/CNY063]
SEQUATCHIE COUNTY SR-8 (RANKIN AVE.) Utility Work both directions from LM 13 to LM 15: Flagger assisted lane closures on SR-8 (Rankin Avenue) between Hwy 28 / Main Street S and Wilhoit Street. Motorists should reduce speed and be prepared to stop. Trucks, arrow board/message boards, flaggers, and barrels/cones will be present, 05/15/25 thru 06/19/25 from 9 am – 2 pm. [2025-317]
WARREN COUNTY SR-1 (US-70S) bridge repair over SR-55 (LM 10.5): The contractor will maintain the closure of one lane on SR-1 on both the EB and WB sides on the bridges with drums. Under the bridge on SR-55 Bypass the portable barrier rail will remain in place long term, closing the outside shoulders under the bridge. Temporary lane and shoulder closures on and surrounding over and under bridge will also be utilized as needed with proper signing. RESTRICTIONS: Maximum width 15 feet both directions. [Mid-State Construction Company, Inc./McMinnville/CNY196]
DISTRICT 29
BRADLEY COUNTY I-75 at Paul Huff Parkway Interchange modifications: During this reporting period, the contractor will continue work on permanent signs. Intermittent flagging operations and temporary lane closures may be necessary. Motorists are advised to reduce speed and use caution in the work zone. [Summers-Taylor, Inc./Cleveland/CNX362]
BRADLEY COUNTY SR-60 widening from the 4-lane north of I-75 (LM 17.2) to SR-306 (LM19.9): During this reporting period, the contractor will continue grading work and install driveways, sidewalk, and curb. Intermittent flagging operations will take place throughout the project during various work activities. The speed limit in the work zone has been reduced to 35 mph. Motorists are advised to use caution in the work zone and watch for flaggers assisting with traffic control. [Summers-Taylor, Inc./Cleveland/CNV130]
BRADLEY COUNTY SR-2 [0-6.2] from Hamilton County Line to Boss Road micro surfacing: The contractor will continue micro surfacing operations on SR2 from the Hamilton County line (LM 0) to Boss Road (LM 6.2). The contractor will flag two (2) mile sections and a pacing vehicle will guide traffic through the work zone during micro surfacing operations. Flagging will begin 8AM each day. Traffic delays are expected during this work.
[Asphalt Paving Systems, Inc./Chattanooga West/CNZ022]
BRADLEY COUNTY SR-306 [0-5.55] from SR60 to SR308 resurfacing: During this reporting period the contractor will continue resurfacing work. Motorists should be aware of workers and construction equipment present during this time. Intermittent flagging of traffic will be necessary while work is occurring. Loose gravel is expected until final surface is placed.
[Asphalt Paving Systems, Inc./Cleveland/CNZ021]
HAMILTON COUNTY I-75 at I-24 Interchange Reconstruction Phase 2: Nightly Lane closures will occur on this project, 9 PM to 6 AM, on I-75 North and South between Exit 1 (East Ridge) and Exit 3A (East Brainerd Road/ SR-320) and on I-24 East and West from Germantown Road to Spring Creek Road, MM182 to MM185, for various construction activities. These closures may temporarily reduce traffic to a single lane. Uniformed police officers will be present in these work zones to assist with traffic management and to enforce traffic laws. (Note: Currently on Thursday night (6/12) the contractor is scheduled to have lane closures on I-24 West from 9 PM to 6 AM. These closures are necessary to shift the current 3 lanes of traffic from the outside edge of the roadway to newly constructed median (inside) lanes from near Germantown Road to South Moore Road. On Sunday night (6/15) the contractor is planning to similarly shift I-24 East traffic in the same general area. All traffic shift work is highly weather sensitive and could be changed or rescheduled to the next available night if weather or the weather forecast is not favorable for its completion during the allotted times. Additional nightly lane closures (9 AM to 6 PM) are scheduled for I-24 West from Sunday (6/15) through Thursday (6/19) for additional striping and traffic control work in preparation for further traffic shifts scheduled for the June 20th weekend.) It may be necessary to do short duration (15 to 30 minutes) rolling roadblocks during the day or night for patching potholes, clearing debris or repairing guardrail, attenuators, etc. Portions of the left lane on North and South Terrace between Germantown Road and Spring Creek Road will remain closed for the installation of drainage structures, sanitary sewers, retaining and noise wall construction. All work is weather permitting. The entrance and exit ramps to I-24 between Belvoir Avenue and Moore Road are currently closed. RESTRICTIONS: I-24 Ramps between Belvoir Ave. and S. Moore Road are closed. [Wright Brothers Construction Company, Inc./Maj Prj – Blevins/DB2101]
HAMILTON COUNTY SR-2 (BRAINERD RD.) Utility Work both directions from LM 14 to LM 15: NIGHTTIME Flagger assisted lane closures on SR-2 (Brainerd Road) between Spring Creek Road and Howell Avenue. Motorists should reduce speed and be prepared to stop. Arrow board/message boards, flaggers, and barrels/cones will be present, 03/03/25 through 06/14/25 from 9 pm – 5 am. [2025-016]
HAMILTON COUNTY SR-319 (HIXSON PK.) Utility Work both directions from LM 10 to LM 13: Flagger assisted lane closures on SR-319 (Hixson Pike) between Ambrose Lane and Dallas Hollow Road. Motorists should reduce speed and be prepared to stop. Trucks, arrow board/message boards, flaggers, and barrels/cones will be present, 06/12/25 thru 06/17/25 from 9 am – 12 pm. [2025-369]
HAMILTON COUNTY SR-320 (E. BRAINERD RD.) Utility Work both directions from LM 0 to LM 1: Flagger assisted lane closures on SR-320 (E. Brainerd Road) from Lee Hwy to Osborne Drive. Motorists should reduce speed and be prepared to stop. Trucks, arrow board/message boards, flaggers, and barrels/cones will be present, 06/16/25 thru 06/19/25 from 9 am – 2 pm. [2025-370]
HAMILTON COUNTY SR-8 (MARKET ST.) TDOT Bridge Inspection both directions at LM 9.68: The inspection of the Chief John Ross Bridge, which carries Market Street over the Tennessee River, is scheduled to be complete at 5 pm on Thursday, June 12. The work is weather-dependent and will be continued on Friday, June 13 if necessary. On Thursday, June 12 the outside lanes in both directions will be closed, and one sidewalk will be closed throughout the day. Motorists are advised to use caution as they approach the bridge, obey temporary traffic control measures, and be ready to merge left.
HAMILTON COUNTY SR-8 (TAFT HWY.) Utility Work southbound from LM 18 to LM 20: Flagger assisted lane closures on SR-8 (Taft Hwy) between Albert Road and James Blvd. Motorists should reduce speed and be prepared to stop. Trucks, arrow board/message boards, flaggers, and barrels/cones will be present, 06/16/25 thru 06/23/25 from 9 am – 2 pm. [2025-388]
HAMILTON COUNTY I-124 (US-27) from I-24 Interchange to South of the Tennessee River Bridge: Daily lane closures are possible between 9 AM and 3:30 PM as the contractor work along the ramps and 4th Street. Motorists are advised to reduce speed in the work zone and watch for flaggers assisting with traffic control. [Stansell Electric Company, Inc./Chattanooga East/CNY900]
HAMILTON COUNTY I-75 at the Hamilton Place Mall interchange: The SR-153 southbound ramp to I-75 northbound has been reduced to one lane. Traffic shifts have been implemented on I-75 northbound, Shallowford Road entrance ramps, and Shallowford Road exit ramps and Hamilton Place Mall exit ramp. Hamilton Loop Road is closed for retaining wall construction and storm drainage installation between the intersections near Markman’s Jewelers and Texas Roadhouse. The contractor has implemented a traffic shift on Hamilton Place Blvd. shifting NB and SB traffic to the east side of the existing roadway from near the I-75 SB on-ramp to near Bams Drive for the installation of storm drainage. The contractor will maintain 1 lane of traffic in each direction throughout this area. The speed limit has been reduced on I-75 throughout the project limits. Nightly lane closures are permitted 8 PM to 6 AM. Motorists should use caution, paying attention to construction signage and watching for construction vehicles and personnel.
[Summers-Taylor, Inc./Chattanooga West/CNX358]
HAMILTON COUNTY SR-2 [11.33-11.92] from Dodds Ave to Seminole Drive tunnel rehabilitation: TRAFFIC SHIFT – Starting 06/04/25, both directions of traffic will be reduced to one lane and both flows of traffic will share the existing east bound tunnel. The west bound traffic will shift across the existing medians to be able to travel through the east bound tunnel. There will be a raised curb and reflective delineators that will divide traffic within the tunnel.
[Stansell Electric Company, Inc./Chattanooga East/CNY192]
HAMILTON COUNTY SR-317 (Apison Pike) improvement project from SR-321 (Ooltewah-Ringgold Road) to east of Layton Lane: Lane closures and flagging operations will be required on SR-317, Apison Pike, for bridge and grading work. The flagging operations will be performed on 06/12/25, 06/13/25, 06/16/25, 06/17/25, and 06/18/25 from 7 AM to 1 PM and 3 PM to 7 PM. Closures will last about 2 hours per location. The contractor will have intermittent flagging operations during daytime non-peak hours for bridge work, delivery of materials and equipment.
[Wright Brothers Construction Company, Inc./Chattanooga East/CNT336]
HAMILTON COUNTY SR-8 (US-127) Stringers Ridge Tunnel cleaning: The Stringers Ridge Tunnel will be closed 06/18/2025 from 8 PM to 6 AM for cleaning. A detour will in effect during the closures to direct traffic to alternative routes. This work is weather permitting. [Diamond Specialized, Inc./Chattanooga West/CNY133]
HAMILTON COUNTY SR-8 (US-41, US-76) Bachman Tubes cleaning: The Bachman Tunnel will be closed 06/19/2025 from 8 PM to 6 AM for cleaning. A detour will in effect during the closures to direct traffic to alternative routes. This work is weather permitting. [Diamond Specialized, Inc./Chattanooga West/CNY133]
MCMINN COUNTY I-75 TDOT Maintenance southbound at MM 51.2: There will be a bridge repair operation performed on 06/17/2025 from 9 AM to 3 PM. 06/18/2025 will be the backup date in case it rains. The slow lane and shoulder will be blocked off for this operation with traffic control and attenuators. Motorists are asked to use caution in this area.
MCMINN COUNTY SR-30 (TENNESSEE AVE.) Utility Work both directions from LM 19 to LM 21: Flagger assisted lane closures on SR-30 from Cooper Street to Sable Road to 6th Street. Motorists should reduce speed and be prepared to stop. Trucks, arrow board/message boards, flaggers, and barrels/cones will be present, 06/06/25 thru 07/31/25 from 9 am – 2 pm. [2025-228]
MCMINN COUNTY SR-30 (US-411) Utility Work both directions from LM 20 to LM 21: Flagger assisted lane closures on SR-30 (US-411) between 7th Street and 3rd Street / Mecca Pike. Motorists should reduce speed and be prepared to stop. Trucks, arrow board/message boards, flaggers, and barrels/cones will be present, 06/05/25 thru 06/30/25 from 9 am – 2 pm. [2025-316]
MCMINN COUNTY SR-33 (TENNESSEE AVE.) Utility Work both directions from LM 0 to LM 10: Flagger assisted lane closures on SR-33 (Tennessee Avenue) from David W Lillard Memorial Hwy to Big Oak Drive. Motorists should reduce speed and be prepared to stop. Trucks, arrow board/message boards, flaggers, and barrels/cones will be present, 06/06/25 thru 07/31/25 from 9 am – 2 pm. [2025-228]
MCMINN COUNTY SR-39 construction of a bridge over Middle Creek (LM 13.4): During this reporting period, the Northbound and Southbound traffic will be reduced to one lane and controlled by traffic signals. County road 567 will be closed to traffic (LOCAL TRAFFIC ONLY) and detoured to SR039. This closure is necessary to perform the bridge replacement. The lane restriction will remain in place until the bridge replacement is completed.
[Whaley Construction, LLC/Chattanooga East/CNX069]
MCMINN COUNTY SR-39 from west of Cook Drive to SR-30 and from SR-310 to the Monroe County Line: During this reporting period, the contractor will continue resurfacing work. Motorists should be aware of workers in the area performing this work. Intermittent lane closures and flagging operations around the work area will be necessary. A temporary lane closure will be necessary on the outside lane of SR-30 at the intersections with SR-39 while work is performed in this area. Work is scheduled to occur between 9 PM and 6 AM. [Rogers Group, Inc./Cleveland/CNZ038]
POLK COUNTY SR-68 construction of bridge over Brush Creek (LM 16.4): During this update period, the contractor will continue phase 2 bridge construction. A temporary traffic signal system is active on SR-68 near LM 16.4. The northbound lane of SR-68 will be closed in the area controlled by the temporary traffic signal system. Motorists are advised to reduce speed and use caution in the work zone. Motorists should also be aware that traffic was recently moved onto a portion of the new bridge and there is a new traffic pattern through the project site.
[Wright Brothers Construction Company, Inc./Cleveland/CNX347]
POLK COUNTY SR-68 over SR-40 the construction of bridges: During this reporting period the contractor will continue installing EPSC measures. Motorists should be aware of workers in the area performing this work. Intermittent flagging operations around the work area may be necessary.
[Wright Brothers Construction Company, Inc./Cleveland/CNZ042]
RHEA COUNTY SR-302 (OLD STAGE RD.) Utility Work both directions from LM 7 to LM 9: Flagger assisted lane closures on SR-302 from Dividing Ridge Road to SR-68 / Watts Bar Hwy. Motorists should reduce speed and be prepared to stop. Trucks, arrow board/message boards, flaggers, and barrels/cones will be present, 06/09/25 thru 06/20/25 from 9 am – 2 pm. [2025-332]
RHEA COUNTY SR-68 (WATTS BAR HWY.) Utility Work both directions from LM 7 to LM 12: Flagger assisted lane closures on SR-68 (Watts Bar Hwy) between SR-27 / Rhea County Hwy and Walker Road. Motorists should reduce speed and be prepared to stop. Trucks, arrow board/message boards, flaggers, and barrels/cones will be present, 06/16/25 thru 06/27/25 from 9 am – 2 pm. [2025-328 & 2025-331]
RHEA COUNTY SR-30 repair of bridge over Tennessee River: The repair of the bridge on S.R. 30 over the Tennessee River (L.M. 17.28): The bridge has been reduced to one lane of traffic under the control of a traffic signal. The contractor will be making repairs under the Tennessee River Bridge. Watercraft users should use caution when accessing the TWRA boating ramp under the bridge in Rhea County. The contractor will have equipment and materials in the area of the access road for the boating ramp. [Mid-State Construction Company, Inc./Chattanooga East/CNY201]
REGION WIDE
REGION 2 The on-call concrete pavement repair at various locations on various Interstate and State Routes: The contractor will be repairing concrete pavement on ramps at I-24 exit 97. The ramps being repaired at exit 97 are the I-24 WB off ramp, the EB off ramp, and the EB on ramp. This work will require the narrowing of each ramp with a minimum open lane width of 10 feet. Please use caution when driving through the work zones.
[Bluegrass Contracting Corporation/Dunlap/CNY295]
REGION 2 Dynamic Message Sign (DMS) Life Cycle Replacement: Shoulder Closures will be in place on Bradley I-75 NB between MM 25 and MM 35, on McMinn I-75 SB between MM 44 and MM 36, and Marion County I-24 WB at MM 156. Trucks will be entering and exiting the work zone during daytime hours. RESTRICTIONS: BRADLEY I-75 NB BETWEEN MM 25 and MM 35 AND MCMINN I-75 SB BETWEEN MM 44 and MM 36 both the inside and outside shoulders will be closed with concrete barrier rail installed. Total width will be 24 feet wide. Wide loads may need to utilize both lanes of traffic through this area. [Davis H. Elliot Construction Company, Inc./Chattanooga East/CNX413]
REGION 2 Installation of new and upgraded curb ramps and other miscellaneous pedestrian safety improvements: The ADA curb ramp upgrades on various State Routes: Construction activities are ongoing along Market Street, Alton Parkway, and Rossville Blvd in Chattanooga. The contractor is working on removing and replacing the concrete sidewalk and curb ramps. The sidewalk will be closed in this area to all users. Lane closures may be required at times for construction activities. Signs and flaggers may be utilized during these lane closures. Motorists should use caution when traveling through the work zone. [Southern Constructors, Inc./Chattanooga East/CNY253]
REGION 2 The drain cleaning on various Interstate and State Routes: Drain cleaning operations are planned on various routes throughout Region 2. This is a mobile operation along the shoulders with impacts to adjacent traffic lanes. Temporary lane closures maybe utilized to complete this work. These operations will occur at night Sunday through Thursday between 8 PM and 6 AM. [Sweeping Corporation of America, Inc./Chattanooga West/CNY226]
REGION 2 The on-call guardrail repair and new guardrail installation on various Interstate and State Routes: The contractor will have short term shoulder and/or lane closures in order to perform guardrail repair. These closures will take place on the interstate nightly Sunday through Thursday from 7 PM to 6 AM and daily Monday through Friday on state routes. At least one travel lane will remain open to traffic at all times on the interstate, and flaggers will be present on state routes during any work that is performed. [Cumberland Guardrail, Inc./McMinnville/CNY105]
REGION 2 The sweeping on various Interstate and State Routes: Sweeping operations are planned throughout Region 2 this reporting period. Sweeping operations are mobile operations along the inside and outside shoulders with impacts to adjacent traffic lanes. These operations will occur at night between 8 PM and 6 AM for interstates and high traffic state routes, while daytime sweeping can be anticipated between 9 AM to 3 PM for lower traffic state routes.
[Sweeping Corporation of America, Inc./Chattanooga West/CNY210]
REGION 2 Thermoplastic retracing on various interstate and state routes: The contractor will be on site in Putnam County performing thermoplastic retracing work along I-40 from LM 33.2 – 39.1. Additional work will be conducted in Dekalb County along SR-26 from LM 15.920 – 28.240. During this work, the contractor will utilize a mobile operation with mobile message boards and an attenuator truck. Motorists are encouraged to slow down as they approach the work and should be aware of the potential of stopped or slowing traffic. [Reynolds Sealing and Striping, Inc./Cookeville/CNZ054]
REGION 2 Various Interstate and SRs – Cable Barrier Repair: The contractor will have short term shoulder and/or lane closures in order to perform cable barrier rail repair. These closures will take place on the interstate nightly Sunday through Thursday from 7 PM to 6 AM and daily Monday through Friday. At least one travel lane will remain open to traffic at all times. Typically, only a shoulder closure will be used in the median, but lane closures will be employed as needed.
[LU, Inc./McMinnville/CNY183]
REGION 2 preventative and unscheduled maintenance of Chattanooga SmartWay Intelligent Transportation System: The contractor may have short term shoulder and/or lane closures to perform preventative or unscheduled maintenance to the local SmartWay Intelligent Transportation System. At least one travel lane will always remain open to traffic. Flaggers will assist with traffic control as needed. [Lumin8 Transportation Technologies, LLC/Chattanooga East/CNX270]
ANDERSON COUNTY, I-75 North near Mile Marker 125.1: On Tuesday, June 17, 2025, motorists should be alert for possible temporary lane closures between the hours of 8 p.m. and 6 a.m. the following morning as crews perform guardrail repairs. Motorists should be alert for workers present, slow or stopped traffic, and use extreme caution through this area.
ANDERSON COUNTY, SR 61 between Bill Key Lane and Old Batley Road: Motorists should be alert for possible daily lane closures during daylight hours through this construction project. Motorists should be alert for slowed or stopped traffic, expect potential delays, and use extreme caution through this area.
BLOUNT COUNTY, SR 162 Pellissippi Parkway between Cusick Road and SR 33: SR 162 is reduced from two lanes to one through this project as construction crews perform bridge work in this area. Motorists should be alert for possible brief rolling roadblocks between the hours of 9 a.m. and 3 p.m. daily, as needed, for blasting operations. Motorists should be alert for changed conditions, workers present and use extreme caution through this area.
BLOUNT COUNTY, US 321 between Long Branch Road and Stables Drive: Motorists should be alert for possible temporary lane closures between the hours of 9 a.m. and 4 p.m. and 7 p.m. to 6 a.m. the following morning through this resurfacing project. Motorists should be alert for slowed or stopped traffic, expect potential delays, and use extreme caution through this area.
CAMPBELL COUNTY, I-75 North and South between Mile Markers 156 and 161: Motorists should be alert for possible lane closures through this project. Motorists should expect potential delays, be alert for slow or stopped traffic, and use extreme caution through this area.
CAMPBELL COUNTY, I-75 North between Mile Markers 131 and 133: Beginning 7 p.m. Thursday, June 12, 2025, through 6 a.m. Sunday, June 15, 2025, I-75 North will be reduced to one lane in this area as crews perform emergency bridge repairs. This lane reductions will be in place around the clock. Motorists should be alert for slow or stopped traffic, expect potential long delays, and use extreme caution through this area.
CAMPBELL COUNTY, SR 63 between Frontier Road/Woodson Lane and Claiborne County Line: Motorists should be alert for possible temporary lane closures between the hours of 8 a.m. to 6 p.m. through this construction project. Motorists should be alert for slowed or stopped traffic, expect potential delays, and use extreme caution through this area.
CAMPBELL COUNTY, SR 63 between SR 297 and Stinking Creek Road: Motorists should be alert for possible temporary lane closures through this construction project. Motorists should be alert for slowed or stopped traffic, expect potential delays, and use extreme caution through this area.
CARTER COUNTY, US 321/SR 67 Bridge over the Doe River between N. Sycamore and N. Main: The US 321/SR 67 Bridge over the Doe River in Elizabethton is closed due to damages sustained during recent storm events. Large truck traffic should seek alternate routes around this area. For current road conditions, go https://smartway.tn.gov/
CARTER COUNTY, US 321/SR 159 between Green Hollow Road and Poga Road: This section of US 321/ SR 159 is closed due to damages sustained during recent storm events. Motorists should seek alternate routes around this area. For current road conditions, go https://smartway.tn.gov/
CARTER COUNTY, SR 37 between Log Miles 1.4 and 1.6: Motorists should be alert for possible temporary lane closures between the hours of 9 a.m. and 3 p.m. through this slope stabilization project. Motorists should be alert for slowed or stopped traffic, expect potential delays, and use extreme caution through this area.
CLAIBORNE COUNTY, SR 63 between Campbell County Line and Hall Lane: Motorists should be alert for possible temporary lane closures between the hours of 8 a.m. and 6 p.m. through this construction project. Motorists should be alert for slowed or stopped traffic, expect potential delays, and use extreme caution through this area.
COCKE COUNTY, I-40 East between Mile Marker 446 and North Carolina State Line: I-40 East is reduced to 1 lane between Mile Marker 446 in Tennessee and Mile Marker 7 in North Carolina due to damages sustained during recent storm events. Traffic wider than 8 ½ feet is prohibited through this area. Wide Loads should follow I-81 North to I-77 South. This area remains a heavily active construction zone as permanent repairs continue. Motorists should be alert for workers and construction equipment entering and exiting the roadway in this work zone. Motorists should be alert that there are areas with no shoulders and no emergency pull off locations through this work zone. There are no services in this area. Motorists should ensure they have plenty of fuel and vehicle is in good mechanical condition traveling through this area. Motorists should expect potential long delays. Motorists should be prepared to stop and be alert for slow or stopped traffic. Motorists should use extreme caution and avoid all distractions traveling through this area. I-40 “Thru Traffic” should continue to follow I-81 North to I-26 East or I-77 South to avoid potential major delays. For current road conditions, go https://smartway.tn.gov/
COCKE COUNTY, US 25/70 between Tennessee State Line and Hot Springs, North Carolina: Thru truck traffic is prohibited on US 25/70 in North Carolina between the Tennessee State Line and Hot Springs, North Carolina. Truck traffic to North Carolina should follow I-81 North to I-26 East or I-77 South. Traffic wider than 10 feet is prohibited on I-26 between Mile Markers 37 and 40.
COCKE COUNTY, SR 35 between Old Newport Highway and Fain Road: Motorists should be alert forpossible temporary lane closures between the hours of 6 a.m. and 6 p.m. through this construction project. Motorists should be alert for workers present, expect potential delays, and use extreme caution through this area.
GRAINGER COUNTY, SR 131 between Log Miles 7 and 8: Motorists should be alert for lane closures through this construction project. Motorists should be alert for workers present, expect potential delays, and use extreme caution through this area.
GREENE COUNTY, SR 107 Bridge over the Nolichucky River: Motorists should be alert for possible temporary lane closures during daylight hours as crews complete final items through this bridge replacement project. Motorists should be alert for workers present and use extreme caution through this area.
GREENE COUNTY, SR 351 Bridge over the Nolichucky River between Clemmer Drive and Sand Bar Road: The SR 351 Bridge over the Nolichucky River is open to one lane traffic controlled by a temporary signal. Motorists should expect delays and use extreme caution in this area. For current road conditions, go https://smartway.tn.gov/
HAMBLEN COUNTY, US 11E/ SR 34 near Depot Street and Jay Bird Road: Motorists should be alert for temporary lane closures and brief stoppages by flagging personnel at various times through this construction project. Motorists should be alert for workers present, expect potential delays, and use extreme caution through this area.
HAMBLEN COUNTY, US 11E/ SR 34 between Depot Street and Hawkins County Line: Motorists should be alert for possible lane closures through this resurfacing project. Motorists should be alert for workers present, expect potential delays, and use extreme caution through this area.
HAWKINS COUNTY, SR 66 between Log Miles 19.2 and 29.8: Motorists should be alert for possible temporary lane closures during daylight hours through this resurfacing project. Motorists should be alert for workers present, expect potential delays, and use extreme caution through this area.
HAWKINS COUNTY, SR 344 between SR 113 and US 11W/SR 1: Motorists should be alert for possible temporary lane closures during daylight hours through this resurfacing project. Motorists should be alert for workers present, expect potential delays, and use extreme caution through this area.
HAWKINS COUNTY, SR 346 near Log Mile 8.2: Motorists should be alert for possible temporary lane closures during daylight hours through this construction project. Motorists should be alert for workers present, expect potential delays, and use extreme caution through this area.
JEFFERSON COUNTY, I-81 North and South between Mile Markers 0 and 7.5: Motorists should be alert for possible lane closures nightly between the hours of 7 p.m. and 6 a.m. the following morning through this resurfacing project. Motorists should be alert for workers present, possible slow traffic, and use extreme caution through this area.
JEFFERSON COUNTY, US 11E/SR 34 at North Chucky Pike: Motorists should be alert for possible lane closures daily between the hours of 9 a.m. and 3 p.m. as crews perform work through this intersection improvement project. Motorists should be alert for workers present and use extreme caution through this area.
JEFFERSON COUNTY, US 25/70/SR 9 over Rimmer Creek (L.M. 13.2) and Koontz Creek (L.M. 14.2): Motorists should be alert for workers present, possible lane closures at various times, and use extreme caution through this construction project.
JOHNSON COUNTY, US 321/SR 159 between Carter County Line and North Carolina State Line: This section of US 321/ SR 159 is closed due to damages sustained during recent storm events. Motorists should seek alternate routes around this area. For current road conditions, go https://smartway.tn.gov/
KNOX COUNTY, I-275 North and South between I-40 and I-640: Motorists should be alert for possible nightly lane closures between the hours of 7 p.m. and 6 a.m. the following morning as crews perform roadwork activities. Motorists should be alert for workers present, slow or stopped traffic, and use extreme caution through this area.
KNOX COUNTY, Various Interstates through Knoxville: Motorists should be alert for possible mobile lane closures nightly between the hours of 8 p.m. and 6 a.m. the following morning as crews perform roadway maintenance activities. Motorists should be alert for workers present, slow or stopped traffic, and use extreme caution in this area.
KNOX COUNTY, US 129/SR 115 Alcoa Highway between Woodson Drive and Cherokee Trail: Motorists should be alert for possible temporary nightly lane closures from 7 p.m. to 6 a.m. the following morning as crews perform roadway construction between Woodson Drive and Cherokee Trail. Motorists should be alert for crews intermittently pacing traffic between Woodson Drive and Cherokee Trail on Alcoa Highway (US 129/State Route 115) daily, as needed, to move equipment and materials within the project limits and to conduct routine roadway maintenance. Disruptions to traffic flow are anticipated to be short in nature. Motorists should be alert for workers present, reduce speed, be alert for slow or stopped traffic, and use extreme caution through this construction project. For project information, go to https://www.tn.gov/tdot/projects/projects-region-1/sr115-us-129-alcoa-highway.html
KNOX COUNTY, US 441/ SR 33 between Woodrow Drive and Gibbs Drive: Motorists should be alert for possible lane closures daily between the hours of 9 a.m. and 3 p.m. as crews perform roadside construction activities. Motorists should be alert for workers present, expect potential delays, and use extreme caution through this construction project.
KNOX COUNTY, US 441/ SR 71 between Simpson Road and Hendron Chapel Road: Motorists should be alert for possible lane closures, workers present, changed conditions, expect potential delays, and use extreme caution through this construction project.
MONROE COUNTY, US 411/ SR 33 Bridge over Little Tennessee River near Log Mile 16.7: Motorists should be alert for lane reductions through this bridge repair project. Motorists should be alert for workers present, possible slow traffic, and use extreme caution through is area. This project is estimated to be complete on or before July 31, 2025.
MONROE COUNTY, US 411 between Log Miles 5.3 and 7.1: Motorists should be alert for possible lane closures nightly between the hours of 7 p.m. and 6 a.m. the following morning through this resurfacing project. Motorists should be alert for workers present, slow or stopped traffic, and use extreme caution through this area.
ROANE COUNTY, I-40 West near Mile Marker 352: On Tuesday, June 17, 2025, motorists should be alert for possible lane closures between the hours of 9 a.m. and 3 p.m. as crews perform roadside remediation activities. Motorists should be alert for workers present, expect potential delays, and use extreme caution through this area.
ROANE COUNTY, I-40 East and West between Mile Markers 356 and 364: Motorists should be alert for possible lane closures nightly between the hours of 7 p.m. and 6 a.m. the following morning through this resurfacing project. Motorists should be alert for workers present, possible slow traffic, and use extreme caution through this area.
ROANE COUNTY, US 70/ SR 1 between SR 326 and Loudon County Line: Motorists should be alert for possible daily lane closures between the hours of 9 a.m. and 3 p.m. as crews perform roadway resurfacing activities. Motorists should be alert for workers present, expect potential delays, and use extreme caution through this resurfacing project.
SCOTT COUNTY, US 27 between SR 63 and Reed Road: Motorists should be alert for possible daily lane closures between the hours of 7 a.m. and 4:30 p.m. as crews perform roadway resurfacing activities. Motorists should be alert for workers present, expect potential delays, and use extreme caution through this resurfacing project.
SEVIER COUNTY, I-40 East and West between Mile Markers 405 and 410: Motorists should be alert for possible lane closures nightly between the hours of 7 p.m. and 6 a.m. the following morning through this resurfacing project. Motorists should be alert for workers present, possible slow traffic, and use extreme caution through this area.
SULLIVAN COUNTY, I-81 North and South between Mile Markers 54 and 58: Motorists should be alert for possible lane closures nightly between the hours of 7 p.m. and 6 a.m. the following morning through this resurfacing project. Motorists should be alert for workers present, slow or stopped traffic, expect delays, and use extreme caution through this area.
SULLIVAN COUNTY, I-81 North and South at Exit 56: Motorists should be alert for possible temporary lane closures as crews perform concrete ramp ramp repairs. Motorist should be alert for workers present, expect potential delays, and use extreme caution in this area.
SULLIVAN COUNTY, SR 93 Bridge over South Fork Holston River and Plant Road: Motorists should be alert for possible lane closures at various times through this bridge repair project. Motorists should be alert for workers present, changed conditions, expect potential delays, and use extreme caution through this area.
SULLIVAN COUNTY, SR 93 at Bloomingdale Road: Motorists should be alert for possible lane closures at various times through this signal upgrade project. Motorists should be alert for workers present, expect potential delays, and use extreme caution through this area.
UNICOI COUNTY, I-26 East between Mile Markers 39 and 40.2: I-26 East is reduced to one lane through this area. All vehicles more than 10 feet in width are restricted/prohibited through this area due to narrow lane with no shoulder. Traffic wider than 10 feet in width should follow the wide load detour using I-81 and I-77. The eastbound exit ramp to Exit 40 (Jackson Love Highway) is open. Motorists should use extreme caution in this area. For current road conditions, go https://smartway.tn.gov/
UNICOI COUNTY, I-26 West between Mile Markers 41.4 and 37: I-26 West is reduced to one lane through this area and shifted to the eastbound side of the interstate. All vehicles more than 10 feet in width are restricted/prohibited through this area due to narrow lanes with no shoulder. Traffic wider than 10 feet in width should follow the wide load detour using I-77 and I-81. The entrance ramp to I-26 West from Jackson Love Highway at Exit 40 is closed. Motorists in Erwin should access I-26 West at Exit 37. Motorists should use extreme caution in this area. For current road conditions, go https://smartway.tn.gov/
UNION COUNTY, SR 33 between Knox County Line and SR 144: Motorists should be alert for possible lane closures at various times through this construction widening project. Motorists should be alert for new traffic patterns, lane shifts, workers present and use caution through this area.
UNION COUNTY, SR 61 between SR 33 and SR 131: Motorists should be alert for possible temporary lane closures during daylight hours through this resurfacing project. Motorists should be alert for workers present, expect potential delays, and use extreme caution through this area.
UNION COUNTY, SR 131 Tazewell Pike between Knox County Line and Grainger County Line: Motorists should be alert for possible temporary lane closures during daylight hours through this resurfacing project. Motorists should be alert for workers present, expect potential delays, and use extreme caution through this area.
WASHINGTON COUNTY, SR 81 Bridge over the Nolichucky River between Taylors Bridge Road and SR 107: Motorists should be alert for possible temporary lane closures during daylight hours as crews complete final items through this bridge replacement project. Motorists should be alert for workers present and use extreme caution through this area.
WASHINGTON COUNTY, SR 81 between Log Miles 10.9 and 17.9: Motorists should be alert for possible temporary lane closures during daylight hours through this resurfacing project. Motorists should be alert for workers present, expect potential delays, and use extreme caution through this area.
WASHINGTON COUNTY, SR 353 Bridge over the Nolichucky River: The SR 353 Bridge over the Nolichucky River is closed due to damages sustained during recent storm events. Motorists should seek alternate routes around this area. For current road conditions, go https://smartway.tn.gov/
RESTRICTIONS
CUMBERLAND COUNTY – CNZ103: Both lanes of Genesis Road (SR-298) are closed from LM 8.35 to LM 9.02.
PUTNAM COUNTY – Horizontal clearance will be restricted to 9FT. NO TRACTOR TRAILERS.
FRANKLIN COUNTY – CNY068: Old Decherd Road at Wagner Creek is closed.
WARREN COUNTY – CNY196: Maximum width 15 feet both directions.
HAMILTON COUNTY – DB2101: I-24 Ramps between Belvoir Ave. and S. Moore Road are closed.
REGION 2 – CNX413: BRADLEY I-75 NB BETWEEN MM 25 and MM 35 AND MCMINN I-75 SB BETWEEN MM 44 and MM 36 both the inside and outside shoulders will be closed with concrete barrier rail installed. Total width will be 24 feet wide. Wide loads may need to utilize both lanes of traffic through this area.