WIDENING PROJECT BETWEEN I-40 AND MAYFAIR DR EXPECTED TO FINISH IN JUNE
TDOT Smart Way map lists an estimated date of completion for the widening project taking place on State Route 28 as being around June 30th, 2025.
Weekdays will see temporary lane closures in both directions until the work is finished.
“State Route 28 both directions in Cumberland County – Between I-40 and MAYFAIR DR., a widening project will cause temporary lane closures on weekdays. This work is expected to be completed by 06/30/2025.
Current Activity:
The contractor continues grading activities throughout the project limits. Paving operations are ongoing throughout the project. Temporary lane closures and/or periodic traffic stoppages will be necessary for construction activities. The contractor has closed North Grace Hill Drive at the existing intersection of SR-28 (US-127) for construction activities. Motorists should utilize South Grace Hill Drive as the detour with appropriate signs. Flaggers and advanced warning signs will accompany any closures. Motorists should use caution while traveling through the work zone.”